File #: 14-2911   
Type: Capital Improvements
In control: City Council A Session
On agenda: 12/11/2014
Posting Language: An Ordinance accepting the lowest qualified bid and awarding a construction contract, including an additive alternate, to TCL Construction Enterprises, Inc. in the amount of $1,965,000.00 in connection with the Leon Creek Greenway Trail Project from Ingram Road to Military Drive, a 2005 Proposition 2 Sales Tax Initiative funded project located in Council District 6; and authorizing an Advance Funding Agreement with Texas Department of Transportation to allow for the construction and maintenance of the Leon Creek Greenway Trail Project from Ingram Road to Military Drive, within their rights-of-way. [Gloria Hurtado, Assistant City Manager; Xavier D. Urrutia, Director, Parks and Recreation]
Attachments: 1. Bid Tabulation for Leon Creek Greenway - Ingram to Military, 2. Site Map for Leon Creek Greenway - Ingram Road to Military Drive, 3. Formal Invitation for Bid and Contract for Leon Creek Greenway - Ingram Road to Military Drive 26-00077, 4. TxDOT Advance Funding Agreement (Leon at Culebra 410), 5. Ordinance 2014-12-11-1012
DEPARTMENT: Parks and Recreation      
 
 
DEPARTMENT HEAD: Xavier D. Urrutia
      
      
COUNCIL DISTRICTS IMPACTED: Council District 6
 
 
SUBJECT:
 
Leon Creek Greenway - Ingram Road to Military Drive
 
 
SUMMARY:
 
This ordinance accepts the lowest qualified bid and awards a construction contract, including an additive alternate, to TCL Construction Enterprises, Inc. in the amount of $1,965,000.00, a 2005 Proposition 2 Sales Tax Initiative funded project.  They will perform construction work in connection with the Leon Creek Greenway Trail Project from Ingram Road to Military Drive, located in Council District 6.  
 
This ordinance also authorizes the execution of an Advance Funding Agreement with the Texas Department of Transportation (TxDOT) to allow for the construction and maintenance of the Leon Creek Greenway Trail Project from Ingram Road to Military Drive, within their rights-of-way.
 
BACKGROUND INFORMATION:
 
The proposed construction project is part of a growing network of interconnected hike and bike trails now known as the Howard W. Peak Greenway Trails system, which is funded through sales tax initiatives approved by voters in May of 2000, May of 2005 and November of 2010.  The objectives of the program are to acquire and preserve open space along San Antonio creekways and to develop multi-use hike and bike trails, trailheads, signage and associated amenities for use by San Antonio residents and visitors.
 
This ordinance will authorize the construction of a hike and bike trail system along the Leon Creek Greenway Trail Project from Ingram Road to Military Drive and will authorize the execution of an Advance Funding Agreement with TxDOT to allow for the construction and maintenance of the Leon Creek Greenway improvements within TxDOT rights-of-way along Ingram Road to Military Drive. The project will consist of approximately 2.2 miles of concrete trails, a trailhead, signage and associated trail amenities and improvements.  Design work was performed by Terra Design Group.  These improvements will become unique additions to the municipal park system's creekways program for hiking, biking, and other recreational uses.
 
The Request for Low Qualified Bids was advertised the last week of September 2014 and the first week of October 2014 in the Hart Beat, the Texas Electronic State Business Daily, the City's website, and announced on the City's public access station TVSA.  Five bids were received.  After reviewing the bidders' qualifications and conducting interviews, TCL Construction Enterprises, Inc. was selected with the lowest qualified bid, including an additive alternate, of $1,965,000.00. A standard construction contract will be executed and a summary of the bids is shown on Exhibit 1.  TCL Construction Enterprises, Inc. currently has one annual contract with the City.  It is anticipated that construction will begin in December 2014 and will be completed by December 2015.  The additive alternate included as part of this contract includes a trail connection from Leon Creek to Potranco Road and associated sidewalk improvements, node signage and amenities.
 
This contract will be awarded in compliance with the Small Business Economic Development Advocacy (SBEDA) Program, which requires contracts be reviewed by a Goal Setting Committee to establish a requirement and/or incentive unique to the particular contract in an effort to maximize the amount of small, minority, and women-owned business participation on the contract. The Goal Setting Committee set a 28% Small Business Enterprise (SBE) subcontracting goal, a 20% Minority/Women Business Enterprise (M/WBE) subcontracting goal, and a 1% African American Business Enterprise (AABE) subcontracting goal. TCL Construction Enterprises, Inc. has committed to 38.1% SBE, 23.1% M/WBE, and 1.6% AABE subcontractor participation.  TCL Construction Enterprises, Inc. is a certified small and minority owned business.
 
 
ISSUE:
 
This ordinance accepts the lowest qualified bid and awards a construction contract, including an additive alternate, to TCL Construction Enterprises, Inc. in the amount of $1,965,000.00, a 2005 Proposition 2 Sales Tax Initiative funded project. This ordinance also authorizes execution of an agreement with TxDOT to allow for the construction and maintenance of the Leon Creek Greenway Ingram Road to Military Drive trail improvements within TxDOT rights-of-way in two locations.
 
 
ALTERNATIVES:
 
As an alternative, City Council could choose not to award this construction contract.  However, re-bidding the project is not recommended as this would not guarantee lower bids and would delay the start of construction for this project.
 
 
FISCAL IMPACT:
 
This project is listed in the FY 2015-2020 Capital Improvement Program Budget and funds have been appropriated from 2005 Proposition 2 Sales Tax Initiative funds.  This is a one-time capital improvement expenditure in the amount of $1,965,000.00 authorized payable to TCL Construction Enterprises, Inc.
 
Funding for operation and maintenance of the city-wide greenway trail system is submitted annually as part of the General Fund budget process as trail miles are completed.
 
There is no fiscal impact associated with the TxDOT Advance Funding Agreement.
 
 
RECOMMENDATION:
 
Staff recommends approval of this ordinance to accept the lowest qualified bid and awarding a construction contract to TCL Construction Enterprises, Inc. in the amount of $1,965,000.00, a 2005 Proposition 2 Sales Tax Initiative funded project.
 
This construction contract was developed utilizing the formal competitive bid process; therefore, a Discretionary Contracts Disclosure Form is not required.
 
Staff also recommends approval of the execution of an agreement with TxDOT to allow for the construction and maintenance of the Leon Creek Greenway Ingram Road to Military Drive trail improvements within TxDOT rights-of-way in two locations.