Posting Language: An Ordinance for construction Olmos Basin Park Improvements, accepting the lowest responsive bid and awarding a construction contract in the amount of $350,000.00, authorized payable to Consolidated Installation Support, LLC., a 2012-2017 Bond funded Project, located in Council District 1. [Peter Zanoni, Deputy City Manager; Mike Frisbie, Director, Transportation and Capital Improvements]
Indexes: 2012-2017 Bonds
Attachments: 1. Map_Olmos Basin, 2. Draft Ordinance, 3. Ordinance 2014-11-13-0900
DEPARTMENT: Transportation and Capital Improvements


DEPARTMENT HEAD: Mike Frisbie


COUNCIL DISTRICTS IMPACTED: Council District 1


SUBJECT:
Contract Award: Olmos Basin Park Improvements Project


SUMMARY:
An ordinance accepting the lowest responsive bid and awarding a construction contract in the amount of $350,000.00, to Consolidated Installation Support, LLC., for construction of the Olmos Basin Park Improvements Project, a 2012-2017 Bond-funded Project, located in Council District 1.


BACKGROUND INFORMATION:
Project Background
On May 12, 2012, San Antonio voters approved the 2012-2017 Bond Program, consisting of five propositions totaling $596 Million. The Bond Program funds will be used on various capital improvement projects to address community infrastructure needs and improve the overall quality of life in San Antonio. As part of that Program, funds in the total amount of $500,000.00 in Parks, Recreation and Open Space Improvements Bond funds were approved for park improvements at Olmos Basin Park, north of Jackson Keller and west of McCullough Avenue, located in Council District 1. The balance of the Project funds approved by voters will be used for design services, environmental services, advertising and project management.

This Project provides for expansion of the existing parking lot and a 2,870 linear feet of new concrete walking trail with lighting to replace the existing cement stabilized base trail. Project construction is anticipated to begin December 2014 and estimated to be completed by July 2015.

Coordination with Parks and Recreation Department will be made to insure accommodations are made to keep the facility accessible to patrons and residents during construction.

Procurement of Services
This Project was advertised for construction bids in September 2014 in the San Antonio Hart Beat, on the City's website, on the Texas Electronic State Business Daily, on TVSA, and through the TCI Small Business O...