File #: 14-1068   
Type: Capital Improvements
In control: City Council A Session
On agenda: 6/5/2014
Posting Language: An Ordinance related to the Hausman Road Project (Loop 1604 to IH 10), a 2007 and 2012 General Obligation Bond funded project, located in Council District 8, increasing the total construction contract as a result of the project now being fully designed as compared to it being only partially designed when the original contract was approved; authorizing an amendment in the increased amount of $9,568,000.00 to the $62,000,000.00 Design-Build Services Agreement with Sundt Construction, Inc. for the design and construction services to reflect actual known design and construction conditions; of which $4,800,000.00 will be reimbursed by San Antonio Water System and $800,000.00 will be reimbursed by CPS Energy; and, an adjustment to the spending plan to accelerate FY 2015 allocated Linear Creekway Park Trails Program funds in amount of $910,000.00 to FY 2014, for the construction of the Huesta Creek Greenway trail. [Peter Zanoni, Deputy City Manager; Mike Frisbie, Director, Transportation and...
Attachments: 1. Project Site Map_Hausman Rd, 2. Draft Ordinance, 3. Ordinance 2014-06-05-0385
Related files: 14-2143
DEPARTMENT: Transportation and Capital Improvements


DEPARTMENT HEAD: Mike Frisbie


COUNCIL DISTRICTS IMPACTED: 8


SUBJECT:

Design-Build Contract Amendment for Hausman Road (Loop 1604 to IH 10)



SUMMARY:

An ordinance authorizing an amendment in the increased total amount not to exceed $9,568,000.00 to the $62,000,000.00 Design-Build Services Agreement with Sundt Construction, Inc. for design and construction services for the Hausman Road (Loop 1604 to IH 10) Project, a 2007 and 2012 General Obligation Bond funded project, located in Council District 8. Of this total amendment amount, $4,800,000.00 will be reimbursed by San Antonio Water System and $800,000.00 will be reimbursed by CPS Energy. This ordinance also adjusts the spending plan to accelerate FY 2015 allocated Linear Creekway Park Trails Program funds in amount of $910,000.00 to FY 2014, for the construction of the Huesta Creek Greenway trail.



BACKGROUND INFORMATION:

Project Background
The Hausman Road (Loop 1604 to IH 10) Project is a 2012 - 2017 General Obligation Bond funded Project that provides for the reconstruction and widening of Hausman Road from Loop 1604 to IH 10 including curbs, sidewalks, bike lanes, a 10 foot shared-use path on the southside, traffic signals and drainage improvements. The Project also includes two Bexar County flood control projects (Low water Crossing 9 and 10), located within the project limits of the City's Hausman Road Project. These projects will replace low water crossings with bridges along Hausman Road from Huntsman to Roadrunner Way and will include channel improvements to Huesta Creek and Maverick Creek. Project construction began in Spring 2014 and is estimated to be completed in Fall 2015.

Previous Council Action
On November 17, 2011 City Council approved, through Ordinance 2011-11-17-0941, a professional civil engineering services contract with Civil Engineering Consultants to provide a schematic of the Hausman Roa...