Posting Language: Ordinance approving a construction contract with Austin Bridge & Road, L.P. in the amount of $8,576,211.70 of which $1,326,081.87 will be reimbursed by San Antonio Water System and $753,493.33 will be reimbursed by CPS Energy for the Goliad Road (Fair Avenue to East Southcross Boulevard) Project, a 2017 Bond funded project. [Roderick Sanchez, Assistant City Manager; Razi Hosseini, Interim Director, Transportation & Capital Improvements]
Attachments: 1. Goliad - Project Map 2.03.20, 2. Bid Tab_Granicus, 3. Draft Ordinance, 4. Staff Presentation, 5. Ordinance 2020-03-05-0158
DEPARTMENT: Transportation & Capital Improvements


DEPARTMENT HEAD: Razi Hosseini, P.E., R.P.L.S.


COUNCIL DISTRICTS IMPACTED: Council District 3


SUBJECT:

Contract Award: Goliad Road (Fair Avenue to East Southcross Boulevard) (2017 Bond Project)


SUMMARY:

An ordinance accepting the lowest responsive bid and awarding a construction contract to Austin Bridge & Road, L.P. in the amount of $8,576,211.70 of which $1,326,081.87 will be reimbursed by San Antonio Water System (SAWS) and $753,493.33 will be reimbursed by CPS Energy for the Goliad Road (Fair Avenue to East Southcross Boulevard) Project, a 2017 Bond funded project, located in Council District 3.


BACKGROUND INFORMATION:

Project Background
On May 6, 2017, voters approved the 2017 Bond Program which authorized $12,937,000.00 for the Goliad Road (Fair Avenue to East Southcross Boulevard) Project located in Council District 3. This Project is a continuation of the Goliad Road Drainage (SE Military Drive to Loop 410) project funded from the 2012-2017 Bond Program.

Work for this Project will include utility improvements, street reconstruction from Fair Avenue to East Southcross Boulevard including curbs, sidewalks and driveway approaches as needed and pavement work on McDougal Avenue from Goliad Road to South Gevers Street. Project construction is anticipated to begin in April 2020 and estimated to be completed by April 2021.

Procurement of Services
This project was advertised on September 23, 2019 for construction bids in the San Antonio Hart Beat, on the City's website, on the Texas Electronic State Business Daily, on TVSA, through the electronic bidding site CivCast and through the TCI small Business Office. Bids were opened on October 22, 2019 and three (3) bids were received. Of these, Austin Bridge & Road, L.P. submitted the lowest responsive bid. A matrix of the bid outcome is included herein.

This contract will be awarded in compliance with the Small Business Economic Development...