File #: 14-1520   
Type: Capital Improvements
In control: City Council A Session
On agenda: 8/21/2014
Posting Language: An Ordinance accepting the lowest responsive bid and awarding a construction contract including one additive alternate in the amount of $603,000.00 to Allbrite Constructors of Texas, Inc. for construction of the Municipal Court Redesign Project located in Council District 1, funded through Municipal Court and Building Maintenance funds and amending the Capital Budget. [Peter Zanoni, Deputy City Manager; Mike Frisbie, Director, Transportation and Capital Improvements]
Attachments: 1. Bid_Tabulation_Municipal Court, 2. Map_Municipal Court_Frank D Wing, 3. Ordinance 2014-08-21-0593
DEPARTMENT: Transportation & Capital Improvements

DEPARTMENT HEAD: Mike Frisbie

COUNCIL DISTRICTS IMPACTED: Council District 1

SUBJECT:
Contract Award: Municipal Court Redesign


SUMMARY:
An ordinance accepting the lowest responsive bid and awarding a construction contract, including one additive alternate, for construction of the Municipal Court Redesign Project, in the amount of $603,000.00, authorized payable to Allbrite Constructors of Texas, Inc., funded through Municipal Court and Building Maintenance funds. Project is located in Council District 1.


BACKGROUND INFORMATION:
Project Background
This Project provides modifications to convert a meeting room into a Judge's Courtroom and renovations to the front lobby. The one additive alternate is to relocate the processing area to the front of the building. These improvements will improve processing of many outstanding traffic tickets by consolidating flow of citizens to the front of the building and enhance the use of security personnel that are located in the lobby entrance. The work in the lobby area will be performed at night to avoid interference with citizens entering and leaving the building during business hours. Project construction is anticipated to begin in September 2014 and estimated to be completed by February 2015.

Procurement of Services
This Project was advertised for construction bids in the San Antonio Hart Beat, on the City's website and the Texas Electronic State Business Daily in June 2014. In addition, the bid announcement was made on TVSA and through the TCI Small Business Office. Plans were also available for review by potential bidders at the office of Alvidrez Architecture, Inc., located at 110 Broadway, San Antonio, Texas. Bids for this project were opened on July 1, 2014 and two bidders responded. Of these, Allbrite Constructors of Texas, Inc., submitted the lowest responsive bid. A matrix of the bid outcome is included herein as Attachment 2.