city of San Antonio


Some of our meetings have moved. View additional meetings.

File #: 13-848   
Type: Street Closures
In control: City Council A Session
On agenda: 11/7/2013
Posting Language: An Ordinance authorizing a Temporary Closure Multi-Year Agreement with the Texas Department of Transportation allowing the temporary street closure of specified State right of way along the San Antonio Rock ā€˜nā€™ Roll Marathon & 1/2 Marathon route. [Peter Zanoni, Deputy City Manager; Anthony Chukwudolue, Interim Director, Public Works]
Attachments: 1. Rock-N-Roll Marathon Multi-Yr Agr.pdf, 2. 2013 Rock n Roll Marathon Route Map.pdf, 3. Draft Ordinance, 4. Ordinance 2013-11-07-0752
DEPARTMENT: Public Works      
 
 
DEPARTMENT HEAD: Anthony Chukwudolue
      
      
COUNCIL DISTRICTS IMPACTED: City-Wide
 
 
SUBJECT:
 
TxDOT Temporary Closure Multi-Year Agreement - Rock 'n' Roll Marathon
 
 
SUMMARY:
 
This ordinance authorizes an agreement with the Texas Department of Transportation (TxDOT) for the temporary closure of State rights of way along Loop 13 (S.W. Military Dr.), Spur 536 (Alamo/Roosevelt/Probandt), US 281, IH 37 and IH 35 in connection with the San Antonio Rock 'n' Roll Marathon & 1/2 Marathon event to be held on November 17, 2013.  Closures will be permitted between 5:30 a.m. to 5:00 p.m.  The term of the Agreement is for one (1) year with a mutual option to extend and change the San Antonio Rock 'n' Roll Marathon & 1/2 Marathon event date each year for four (4) additional years.
 
 
BACKGROUND INFORMATION:
 
On November 17, 2013 the City will be co-sponsoring the annual San Antonio Rock 'n' Roll Marathon & 1/2 Marathon. This event attracts over 30,000 runners in addition to tens of thousands of volunteers and spectators.  This year's event will once again include a bicycle tour of the route, which will begin just prior to the start of the race.  In order to ensure a safe environment for all participants the closure of various roadways is required.
 
 
 
 
ISSUE:
 
Several of the roadways to be used during this year's Rock 'n' Roll Marathon event are state-owned roadways and authorization for temporary closure is needed from TxDOT.  Based on TxDOT policy, authorization for temporary closures of state-maintained roadways is formally granted by agreement, which must be executed between governmental jurisdictions which will be impacted by the temporary road closures.  Public Works Department staff, in coordination with Downtown Operations and San Antonio Police Department (SAPD), has developed the Traffic Control Plan that will be utilized during the temporary street closures. SAPD will be responsible for directing traffic along the detour route.  
 
This City Council action will ensure that the temporary street closure will be permitted for this event.
 
This ordinance authorizes the execution of the Temporary Closure Agreement between the TxDOT and the City of San Antonio (COSA) providing for the temporary street closure along segments of Loop 13 (S.W. Military Dr.), Spur 536 (Alamo/Roosevelt/Probandt), US 281, IH 37 and IH 35 on November 13, 2011 between the hours of 5:30 a.m. to 5:00 p.m. The term of the Agreement is for one (1) year with a mutual option to extend and change the San Antonio Rock 'n' Roll Marathon & 1/2 Marathon event date each year for four (4) additional years.
 
 
 
 
ALTERNATIVES:
 
The City Council could choose not to approve this agreement, which would result in the temporary street closures on State right of ways not being permitted.
 
 
 
FISCAL IMPACT:
 
There is no fiscal impact associated with this action.
 
 
RECOMMENDATION:
 
Public Works staff recommends approval of the Temporary Closure Multi-Year Agreement between TxDOT and the City of San Antonio for the temporary street closure of Loop 13 (S.W. Military Dr.), Spur 536 (Alamo/Roosevelt/Probandt), US 281, IH 37 and IH 35 associated with the San Antonio Rock 'n' Roll Marathon & 1/2 Marathon.