Posting Language: An Ordinance authorizing a task order to an On Call Contract Services provider in an amount not to exceed $220,000.00 payable to Craftsmen Plumbing, for a Central Police Patrol Facility plumbing system repair, a Facilities Deferred Maintenance Funded Project, located in Council District 1. [Ben Gorzell, Chief Financial Officer; Jorge A. Perez, Director, Building and Equipment Services]
Attachments: 1. 515 Frio Map.pdf, 2. Discrecionary Disclosure Form.pdf, 3. Ordinance 2014-06-19-0451
DEPARTMENT: Building and Equipment Services


DEPARTMENT HEAD: Jorge A. Perez


COUNCIL DISTRICTS IMPACTED: 1


SUBJECT:

Contract Award: On Call Contracting Services (OCCS) Central Police Patrol Facility Plumbing Improvements



SUMMARY:

An ordinance authorizing a task order to an On Call Contract Services provider (OCCS), in an amount not to exceed $220,000.00 payable to Craftsmen Plumbing, for a Central Police Patrol Facility plumbing system repair, a Facilities Deferred Maintenance Funded Project, located in Council District 1.


BACKGROUND INFORMATION:

The building located at 515 S Frio was originally constructed as a warehouse and in the late 1970s, was converted into the Public Safety Technology Center where the Information Technology Support Department (ITSD) and Central Police Station are located. The main sewage piping system currently installed in the facility is the original system and has exceeded its life expectancy.

Procurement of Services:
This Project was selected to utilize the On Call Contract Services provider, an alternative project delivery method which ten contractors were approved through Ordinance 2011-0414-0292 by City Council on 14 April, 2011. The use of the OCCS delivery method provides the City with on-call construction, renovation and maintenance services for City buildings and facilities. Assignment of OCCS contractors to specific jobs is based on the contractor's current workload, overall capacity, and familiarity with a specific facility, expertise in completing specific task and/or managing a specific trade needed to carry out the requested repair or rehabilitation. Of the ten contractors, Craftsman Plumbing was selected to submit an estimate and project schedule for this Project.
The OCCS contract associated with this agreement was advertised in 2010, prior to the implementation of the revised SBEDA ordinance. Therefore, the solicitation required respondents to make a good faith eff...