DEPARTMENT: Office of EastPoint & Real Estate Services
DEPARTMENT HEAD: Mike Etienne
COUNCIL DISTRICTS IMPACTED: 10
SUBJECT: Joint Use Agreement: SAWS use of City-owned property
SUMMARY:
An ordinance authorizing four (4) Joint Use Agreements between the City of San Antonio and the San Antonio Water System (SAWS) to include a 0.171 acre within Drainage Right-of-Way within Heatherwood Subdivision, 0.481 acre within Drainage Right-of-Way within Heatherwood Subdivision, 1.209 acre within Woodstone Subdivision, and 0.378 acre within a city-owned drainage right-of-way within the Raintree Subdivision, in Council District 10, for a total of $3,720.00.
BACKGROUND INFORMATION:
The far northeast quadrant of SAWS' service area drains by gravity to the Cibolo Creek Municipal Authority's (CCMA) collection system. Currently, SAWS conveys raw wastewater to the CCMA for treatment. Cibolo Creek Municipal Authority recently increased its rates, so it is now more economical for SAWS to construct infrastructure to reroute the flow to the Eastern Sewershed for treatment at the Dos Rios Water Recycling Center.
The SAWS infrastructure project scope to reroute the waste from Cibolo Creek Municipal Authority's collection system to the Dos Rios Water Recycling Center includes design and installation of two lift stations, gravity mains and force mains. The estimated construction cost is $8,098,902.00. SAWS construction is to begin in May, 2015 and will be completed in September, 2016.
ISSUE:
An ordinance authorizing four (4) Joint Use Agreements between the City of San Antonio and the San Antonio Water System (SAWS) to include a 0.171 acre within Drainage Right-of-Way within Heatherwood Subdivision, 0.481 acre within Drainage Right-of-Way within Heatherwood Subdivision, 1.209 acre within Woodstone Subdivision, and 0.378 acre within a city-owned drainage right-of-way within the Raintree Subdivision, in Council District 10, for a total of ...
Click here for full text