Posting Language: An Ordinance for the Espada Road Project, a 2012-2017 Bond Program-funded project, located in Council District 3, authorizing the acquisition, through negotiation or condemnation, of approximately 0.685 acres for interests in land sufficient for project purposes in a portion of three parcels of privately-owned real property located in NCBs 11173 and 11168, and declaring it a public use project for the acquisition, and authorizing expenditures not to exceed $82,500.00, payable to the selected title company, for land, relocation, litigation expenses and associated title fees. [Peter Zanoni, Deputy City Manager; Mike Frisbee, Director, Transportation & Capital Improvements]
Attachments: 1. Espada Road map, 2. Field Notes-Espada, 3. Ordinance 2015-04-09-0283
DEPARTMENT: Transportation and Capital Improvements


DEPARTMENT HEAD: Mike Frisbie, PE


COUNCIL DISTRICTS IMPACTED: Council District 3


SUBJECT:

Acquisition: Real Property for Espada Road (Loop 410 to East Ashley Road) Project


SUMMARY:

An ordinance for the Espada Road (Loop 410 to East Ashley Road) Project, a 2012-2017 Bond Program-funded project, located in Council District 3; authorizing the acquisition, through negotiation or condemnation, of approximately 0.685 acres for interests in land sufficient for project purposes in a portion of three parcels of privately-owned real property located in NCBs 11173 and 11168; and declaring it to be a public use project for the acquisition and authorizing expenditures not to exceed $82,500.00, payable to the selected title company, for land, relocation, litigation expenses and associated title fees.

Pursuant to enacted Texas Senate Bill 18 (SB "18"), this item requires City Council to initiate a motion authorizing the use of power of eminent domain, should it be needed.


BACKGROUND INFORMATION:

The Espada Road (Loop 410 to East Ashley Road) Project was included in the 2012-2017 Bond Program. The Project includes the reconstruction and widening of Espada Road (Loop 410 to East Ashley Road), to include bike lanes, lighting, aesthetic enhancements and drainage improvements. Project construction is estimated to begin in Spring 2015 and is estimated to be completed in July 2016.

This Project requires the acquisition of 32 parcels of privately-owned real property by negotiation or condemnation, if necessary, for the construction of the Espada Road (Loop 410 to East Ashley Road) Project. Currently 29 of the 32 parcels have been acquired or are in the process of being acquired through negotiation. However, the remaining three parcels may require the power of eminent domain.

The City intends to use every effort available to obtain the required parcels for said Project through ...