city of San Antonio


Some of our meetings have moved. View additional meetings.

File #: 15-3529   
Type: Purchase of Services
In control: City Council A Session
On agenda: 6/18/2015
Posting Language: An Ordinance authorizing a contract with Active Network to provide the City with a standardized, modern enterprise platform for processing, reporting and managing payment transactions, and a system for accessing City events and facilities, with an estimated contract value of $1.73 million for year one for both POS and RRS systems and $254,000.00 annual costs thereafter for software maintenance and subscription fees, funded through Capital Project Sources (Tax Notes). [Ben Gorzell, Chief Financial Officer; Troy Elliott, Director]
Attachments: 1. RFCSP, 2. Score Summary, 3. Contracts Discloure Form, 4. Ordinance 2015-06-18-0527
DEPARTMENT: Finance


DEPARTMENT HEAD: Troy Elliott


COUNCIL DISTRICTS IMPACTED: City Wide


SUBJECT:
Customer First San Antonio (C1SA) Project - Software and Implementation Services for Point-of-Sale and Reservation/Registration Systems


SUMMARY:
This Ordinance authorizes a contract with The Active Network, Inc., to provide the City Departments' and residents with a standardized, modern enterprise platform for processing, reporting and managing payment transactions through a new Point of Sale System (POS) as well as a Reservation and Registration System (RRS) for increasing public access to a wide range of City events and facilities. The systems will meet Payment Card Industry (PCI) compliance standards, inclusive of new Europay, MasterCard and Visa (EMV) requirements. The estimated contract value for the proposed solution from Active Network is $1.73 million for the software and implementation for both POS and RRS and $254,000 annually thereafter for software maintenance and subscription fees. The total cost of the project inclusive of Active costs, hardware and installation costs, and other professional services is $2.63 million. This project will be funded with $1.73 million from the Capital Budget. The $890,397 above and beyond the current Capital Budget funding will be requested through the Budget process. The estimated cost breakdown for the project is as follows:

POS (Active Payment Manager)
Implementation Services - Active
$ 271,742
Software & Licensing - Active
$1,033,500
Other Professional Services
$ 360,000
Hardware & Installation
$ 444,500
Year 1 Software Maintenance
$ 81,125
Contingency
$100,000
POS Subtotal
$2,290,867

RRS (Active Net)
Implementation Services - Active
$ 152,800
Other Professional Services
$ 25,000
Hardware & Installation
$ 65,000
Annual Subscription
$ 60,730




Contingency
$ 30,000
RRS Subtotal
$ 333,530
PROJECT TOTAL
$2,624,397


BACKGROUND INFORMATION:
Submitted for City Counci...

Click here for full text