Posting Language: Consideration to approve the following three facility improvement projects totaling approximately $24,850.00 funded by $2.6 million in remaining capital construction project funds: [Kathy Bruck, Pre-K 4 SA CEO] a.) Installation of a shade window cover at the North Education Center for approximately $700.00 b.) Installation of carpeting in the South Education Center Training Rooms for approximately $17,650.00 c.) Construction of an additional Family Specialist office at the South Education Center for approximately $6,500.00
Indexes: Pre-K 4 SA
Related files: 15-1004, 15-4446
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
DEPARTMENT: Pre-K 4 SA


DEPARTMENT HEAD: Kathy Bruck, CEO


COUNCIL DISTRICTS IMPACTED: City Wide


SUBJECT:

Pre-K 4 SA Facility Improvement Projects


SUMMARY:

This item requests Board approval for facility improvement projects at the South and North Education Centers which amount to approximately $24,850.00 to be funded by $2.6 million in project funds which were approved during the March 3, 2015 Board meeting and have already funded approximately $48,000.00 of facility improvement projects for the Education Centers to date.

BACKGROUND INFORMATION:

During the March 3, 2015 meeting, the Board of Directors approved for Pre-K 4 SA to accept approximately $2.6 million in funds originally allocated to the construction of Pre-K 4 SA Education Centers which the program would utilize for additional facility improvement projects. Since then, Pre-K 4 SA has utilized the funding on the following facility improvement projects:

Project
Education Center
Total Cost
Dirt for Erosion
North Education Center
$900.00
Deck for Erosion
North Education Center
$29,655.00
Teacher Work Room
South Education Center
$9,838.00
HVAC/Sprinklers for Offices
South Education Center
$6,902.00
Total

$47,295.00

The Transportation and Capital Improvement Department (TCI) issued orders utilizing a City Council approved JOC contract with Con-Cor Inc. to complete the aforementioned facility improvement projects at the North and South Education Centers.

ISSUE:

Pre-K 4 SA requests approval for additional improvement projects which will exceed $50,000.00 in services from the City Council approved JOC contract with Con-Cor Inc. These projects include the following:

Project
Education Center
Approximate Cost
Shade Window Cover
North Education Center
$700.00
Carpet for Training Rooms
South Education Center
$17,650.00
Additional Office
South Education Center
$6,500.00
Total

$24,850.00

In order to complete the various facility improvement projects to the North ...