DEPARTMENT: Transportation & Capital Improvements
DEPARTMENT HEAD: Mike Frisbie, P.E.
COUNCIL DISTRICTS IMPACTED: City Wide
SUBJECT:
Contract Awards for Street Maintenance Projects
SUMMARY:
Consideration of four task order contracts related to the FY 2016-2020 Infrastructure Management Program (IMP):
A. An ordinance awarding an Asphalt Overlay Contract to Clark Construction of Texas, Inc. in an amount not to exceed $8,618,595.00 of which $211,550.00 will be reimbursed by San Antonio Water Systems (SAWS) and $29,250.00 by CPS Energy.
B. An ordinance awarding an Asphalt Overlay Contract to J&P Paving Company, Inc. in an amount not to exceed $4,091.381.80 of which $143,650.00 will be reimbursed by San Antonio Water Systems (SAWS) and $9,550.00 by CPS Energy.
C. An ordinance awarding an Asphalt Overlay Contract to Clark Construction of Texas, Inc. in an amount not to exceed $8,805,694.20 of which $118,950.00 will be reimbursed by San Antonio Water Systems (SAWS) and $36,300.00 by CPS Energy.
D. An ordinance awarding an Asphalt Overlay Contract to J&P Paving Company, Inc. in an amount not to exceed $3,806,532.28 of which $121,800.00 will be reimbursed by San Antonio Water Systems (SAWS) and $9,950.00 by CPS Energy.
BACKGROUND INFORMATION:
Project Background
City Council approved $64 million in the FY 2016 Budget to complete both in-house and contract street maintenance projects. Of this amount, approximately 97 miles and $54 million in street maintenance projects will be completed through the use of construction contractors. These contracts also will be utilized to complete $400,000.00 of bus pads funded with the City's Advanced Transportation District funds, $595,950.00 of utility adjustments to be reimbursed by SAWS and $85,050.00 of utility adjustments to be reimbursed by CPS Energy.
The Transportation & Capital Improvements Department solicited bids for construction services and will be utilizing various constr...
Click here for full text