city of San Antonio


Some of our meetings have moved. View additional meetings.

File #: 16-2388   
Type: Staff Briefing - Without Ordinance
In control: Neighborhoods and Livability Committee
On agenda: 3/29/2016
Posting Language: Briefing and update on the draft Brackenridge Park Master Plan. [María Villagómez, Assistant City Manager; Janet Martin, Interim Director, Parks and Recreation]
Related files: 16-2132
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
DEPARTMENT: Parks and Recreation


DEPARTMENT HEAD: Janet Martin


COUNCIL DISTRICTS IMPACTED: Council District 1 & 2


SUBJECT:

Briefing on Draft Brackenridge Park Master Plan


SUMMARY:

Briefing and update on the Draft Brackenridge Park Master Plan


BACKGROUND INFORMATION:

In April 2015 City Council approved the development of a master plan for Brackenridge Park through a professional services agreement with Rialto Studio, Inc. The project team includes Rialto Studio, Inc. along with Alamo Architects, Ford Powell & Carson, and Work5hop. The Brackenridge Park Conservancy has also assisted the project team in the master plan process and has been actively engaged in stakeholder outreach and meetings.

In July 2015 the project team and Brackenridge Conservancy held a public workshop at the D.R. Semmes Family YMCA at Tripoint. Main themes from the public meeting included park traffic, park accessibility, and parking. Subsequent to the public meeting individual stakeholder meetings were conducted through November 2015. Through feedback from the public workshop and park stakeholder meetings the draft master plan was developed and presented to the Parks and Recreation Department on March 2, 2016.

The draft master plan identifies primary park issues such as segmented functionality and flow; the dominance of impervious cover; lack of parking; constricted roadway access; invasive species; river quality; neighborhood pedestrian connectivity; limited free public space; and costly park maintenance activities. To address these challenges the master plan project team identified five (5) goals: 1) clarification of the park perimeter; 2) enlarging the park; 3) strengthening pedestrian park flow along the river; 4) balancing the park use portfolio; and 5) establishing park community support.

The project team will hold meetings this spring to present outcomes and recommendations of the Draft Brackenridge Park Master Plan to the...

Click here for full text