city of San Antonio


Some of our meetings have moved. View additional meetings.

File #: 16-2478   
Type: Staff Briefing - Without Ordinance
In control: Transportation, Technology and Utilities Committee
On agenda: 4/13/2016
Posting Language: Briefing on Transportation Improvement Program Funding through the Alamo Area Metropolitan Planning Organization. [Peter Zanoni, Deputy City Manager; Mike Frisbie, Director, Transportation & Capital Improvements]
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

DEPARTMENT:  Transportation and Capital Improvements (TCI)

 

DEPARTMENT HEAD:  Mike Frisbie

 

COUNCIL DISTRICTS IMPACTED:  Citywide

 

SUBJECT:  2017-2020 Alamo Area MPO Transportation Improvement Program (TIP)

 

SUMMARY: 

The Transportation and Capital Improvements (TCI) Department will provide a briefing on the 2017-2020 Alamo Area Metropolitan Planning Organization (MPO) Transportation Improvement Program (TIP)

 

BACKGROUND INFORMATION:

Projects have been selected for inclusion in the 2017-2020 Alamo Area MPO Transportation Improvement Program (TIP).  The revenue for this call for projects utilized federal Surface Transportation Program - Metropolitan Mobility (STP-MM) funds.  Projects in this TIP are anticipated to be let for construction in years 2019-2022.  The MPO Policy Board took action on the projects at their March 28 meeting and will take final action to update the TIP on April 25 meeting. 

 

ISSUE:

The MPO issued a call for projects to this region’s transportation partner agencies in June, 2015.  At the time, there was an estimated $100 million available.  This estimate since has been increased to over $150 million.  San Antonio submitted eight (8) projects that totaled $92 million for this project call.

 

The projects approved include $32 million in construction dollars for the City-submitted projects.  Although two projects will not receive funding, they will be placed in Appendix D of the TIP so that they may proceed with environmental clearance.  $24 million recommended for our partner agencies also will significantly benefit San Antonio citizens (this includes the Broadway Corridor submitted by TxDOT and Pedestrian Safety enhancement projects submitted by VIA).

 

ALTERNATIVES:

This is a briefing for information purposes only.

 

FISCAL IMPACT:

A 20% local match for construction will be required City led projects utilizing IMP and Bond already in the City’s Five Year Capital Improvement Program.

 

RECOMMENDATION:

This is a briefing for information purposes only.