Posting Language: An Ordinance authorizing a task order to a Job Order Contract with Con-Cor, Inc., in an amount not to exceed $122,142.52 for sewer line replacement at the Central Police Substation, a FY 2016 Deferred Maintenance Program funded project, located in Council District 5. [Peter Zanoni, Deputy City Manager; Mike Frisbie, Director, Transportation & Capital Improvements]
Attachments: 1. Disclosure Form_Central Police Sewer, 2. Utilization Plan_Central Police Sewer, 3. Proposal Letter for Central Police Sewer Line Replacement, 4. Central Police Sewer Line Map, 5. Draft Ordinance, 6. Ordinance 2016-04-28-0297
DEPARTMENT: Transportation & Capital Improvements


DEPARTMENT HEAD: Mike Frisbie, P.E


COUNCIL DISTRICTS IMPACTED: Council District 5


SUBJECT:

Contract Award: (Job Order Contract) Central Police Substation Sewer Line Replacement


SUMMARY:

An ordinance for the Central Police Substation Sewer Line Replacement Project authorizing a task order to a Job Order Contract with Con-Cor, Inc., in an amount not to exceed $122,142.52, for an FY 2016 Deferred Maintenance Program funded project, located in Council District 5.


BACKGROUND INFORMATION:

As part of the FY 2016 Deferred Maintenance Program, $200,000.00 was included for the renovation of the Central Police Substation men's and women's restrooms located at 515 Frio St. The balance of the project funds will be used for design services, advertising, and project management. Any remaining funds will be realized as savings.

The existing cast iron sewer lines to the men's and women's restroom are corroded and leaking beyond repair and need to be replaced. This project provides removal of all existing sewer waste lines for the men's and women's restrooms and replacement of the drain lines for the water fountain, and complete replacement and installation of new urinals, new fixtures, new floor drains, and new PVC piping in the East bathroom.


Procurement of Services
This project was selected to utilize the Job Order Contracting (JOC), an alternative project delivery method, through which 10 contractors were approved through Ordinance 2015-01-15-0013 by City Council on January 15, 2015. The use of the JOC delivery method has provided the City with on-call construction, renovation and maintenance services for City buildings and facilities. Assignment of a JOC contractor to a specific job is based on the contractor's current workload, overall capacity, familiarity with a specific facility, expertise in completing specific task(s) and/or managing a specific trade needed to carry out...