city of San Antonio


Some of our meetings have moved. View additional meetings.

File #: 16-5832   
Type: Capital Improvements
In control: City Council A Session
On agenda: 1/12/2017
Posting Language: An Ordinance for the Alamodome Renovation Project authorizing a $700,000.00 amendment to the existing $49,427,484.00 Design-Build Contract with Turner Construction Company for energy efficiency improvements to the Alamodome’s interior lighting funded from the City’s Energy Efficiency Fund, located in Council District 2. [Peter Zanoni, Deputy City Manager; Mike Frisbie, Director, Transportation & Capital Improvements]
Attachments: 1. Site Map Alamodome, 2. Alamodome Form 1295 signed, 3. Draft Ordinance, 4. Ordinance 2017-01-12-0005
DEPARTMENT: Transportation & Capital Improvements


DEPARTMENT HEAD: Mike Frisbie, P.E.


COUNCIL DISTRICTS IMPACTED: Council District 2


SUBJECT: Amendment - Alamodome Renovation Project


SUMMARY:

An ordinance for the Alamodome Renovation Project authorizing an amendment to the existing Design-Build Contract with Turner Construction Company, increasing the contract amount by $700,000.00 for a total contract value not to exceed $50,127,484.00 for energy efficiency improvements to the Alamodome lighting, available from the Energy Efficiency Fund, located in Council District 2.


BACKGROUND INFORMATION:

In November 2014, the NCAA selected the City of San Antonio to host the NCAA Men's College Basketball Final Four Tournament in 2018 at the Alamodome. A contributing factor of the City winning the bid relied on the integrated nature of the Alamodome and Henry B. Gonzalez Convention Center, along with the City's commitment to have the Alamodome's renovations substantially completed by November 1, 2017.

The Project includes the demolition and expansion of the Alamodome's north plaza, expansion of the concourses at plaza level on the east and west sides of the facility, renovation of locker rooms and IT upgrades, to include scoreboards, ribbon boards and an associated control room. Construction schedule and activities shall be coordinated to work around the daily Alamodome operations, with both planned and future events taking place in the facility.

Project design is complete; early works construction began in January of 2016 with overall substantial completion scheduled on or before November 1, 2017. Final completion will occur by November 30, 2017. Below is a list of key construction elements for the project.

Key Construction Elements:
* Technology Upgrades
* Locker Room Renovations
* North Plaza Expansion
* Concourse Expansion
* Concourse Concession Equipment Upgrades




Previous Council Action:


Item
Action Item
Date
Cost Amount
Original
Design Bu...

Click here for full text