FY 2018 Pavement Preservation Task Order Contracts
SUMMARY:
Consideration of the following items related to the FY 2018 Infrastructure Management Program (IMP):
A. An ordinance for the 2018 Micro-Surface Task Order Contract Package 1, accepting the lowest responsive bid and awarding a contract to Viking Construction, Inc. in an amount not to exceed $1,677,060.00, of which $16,800.00 will be reimbursed by San Antonio Water System for necessary adjustments to its existing infrastructure.
B. An ordinance for the 2018 Fog Seal Task Order Contract Package 1, accepting the lowest responsive bid and awarding a contract to Clark Construction of Texas, Inc. in an amount not to exceed $1,286,122.50, of which $12,500.00 will be reimbursed by San Antonio Water System for necessary adjustments to its existing infrastructure.
C. An ordinance for the 2018 Micro-Surface Task Order Package 2, accepting the lowest responsive bid and awarding a contract to Intermountain Slurry Seal, Inc. in an amount not to exceed $3,238,777.00, of which $65,625.00 will be reimbursed by San Antonio Water System for necessary adjustments to its existing infrastructure.
D. An ordinance for the 2018 Onyx Task Order Contract Package 1, accepting the lowest responsive bid and awarding a contract to Clark Construction of Texas, Inc. in an amount not to exceed $975,227.75, of which $14,000.00 will be reimbursed by San Antonio Water System for necessary adjustments to its existing infrastructure.
E. An ordinance for the 2018 Base Repair Task Order Contract Package 1, accepting the lowest responsive bid and awarding a contract to All In Construction, L.L.C. in an amount not to exceed $488,319.80, of which $16,000.00 will be reimbursed by San Antonio Water System for necessary adjustments to its existing infrastructure.
BACKGROUND INFORMATION:
City Coun...