Department: Development Services
SUBJECT:
Wilderness Oak Center Phase IIA & III 140412
SUMMARY:
Request by Ben Scott, HEB Grocery Company, LP. A Texas Limited Partnership, for approval of a three (3) year time extension in accordance with Section 35-430(f)(2) of the City of San Antonio’s Unified Development Code (UDC), for Wilderness Oak Center Phase IIA & III
Subdivision, generally located north of the intersection of Wilderness Oak and Summerglen Way. Staff recommends Approval. (Juanita Romero, Planner, (210) 207-8264, Juanita.romero@sanantonio.gov, Development Services Department)
BACKGROUND INFORMATION:
Council District: 9
Filing Date: March 30, 2018
Owner: Ben Scott, HEB Grocery Company, LP. A Texas Limited
Partnership
Engineer/Surveyor: Stantec Consulting Services Inc.
Staff Coordinator: Juanita Romero, Planner, (210) 207-8264
ANALYSIS:
The applicant is requesting a three (3) year time extension in order to fulfill the improvements required and execute a modified Utility Service Agreement (USA) acceptable to SAWS. Said modifications have started on construction; however, have halted due to the current expiration date of the plat set for June 1, 2018.
Case History:
The Planning Commission approved this plat on June 2, 2015. The plat has not been recorded.
Alternative Actions:
The Planning commission can Approve, Approve as Amended, or Disapprove the request for time extension, as per section 35-430(f)(2) of the Unified Development Code.
RECOMMENDATION:
Approval of a three (3) year time extension for completion of the required site improvements in accordance with the City of San Antonio’s Unified Development Code Section 35-430(f)(2).