city of San Antonio


Some of our meetings have moved. View additional meetings.

File #: 18-3345   
Type: Capital Improvements
In control: City Council A Session
On agenda: 5/17/2018
Posting Language: Ordinance for the 2017 Bond Program Pedestrian Mobility & Streets Task Order Contract Package 2, approving a task order contract to San Antonio Concepts Construction, LLC in the amount not-to-exceed $2,392,929.23, of which an estimated $96,406.00 will be reimbursed by San Antonio Water System and an estimated $2,000.00 will be reimbursed by CPS Energy for necessary adjustments to its existing infrastructure.
Attachments: 1. Item A. Bid Tab (Task Order 2), 2. Item B. Bid Tab (Task Order 5), 3. Ordinance 2018-05-17-0349
Related files: 18-3347, 18-2734
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
DEPARTMENT: Transportation & Capital Improvements (TCI)


DEPARTMENT HEAD: Mike Frisbie, P.E


COUNCIL DISTRICTS IMPACTED: 1, 2, 3, 4, 5, 6, 7 & 9


SUBJECT:

2017 Bond Program Pedestrian Mobility & Streets Task Order Contract Packages 2 and 5.


SUMMARY:

Consideration of the following ordinances related to the Pedestrian Mobility & Streets, 2017 - 2022 Bond Program Projects, to be located in Districts 1, 2, 3, 4, 5, 6, 7, and 9:

A. Ordinance for the Pedestrian Mobility & Streets Task Order Contract Package 2 accepting the lowest responsive bid and awarding a task order contract to San Antonio Concepts Construction, LLC in the amount not-to-exceed $2,392,929.23, of which $96,406.00 will be reimbursed by San Antonio Water System (SAWS) and $2,000.00 will be reimbursed by CPS Energy for necessary adjustments to its existing infrastructure.

B. Ordinance for the Pedestrian Mobility & Streets Task Order Contract Package 5 accepting the lowest responsive bid and awarding a task order contract to Pinnacle Concrete Construction, LLC in the amount not-to-exceed $2,256,948.00, of which $167,400.00 will be reimbursed by San Antonio Water System (SAWS) and $2,500.00 will be reimbursed by CPS Energy for necessary adjustments to existing infrastructure.



BACKGROUND INFORMATION:

On May 6, 2017, voters approved the 2017-2022 Bond Program, which authorized $48 million for Pedestrian Mobility & Street improvement projects in Districts 1, 2, 3, 4, 5, 6, 7, and 9. These contracts will be utilized to complete sidewalks to accomplish the project scope. Projects are being identified and selected through coordination with TCI staff and respective Council District office.

These contracts were advertised in the San Antonio Hart Beat, on the City's website, on the Texas Electronic State Business Daily and on TVSA on:

Package
Advertised
Due|1010|February 2018
February 2018|1010|March 2018
March 2018

Previous Council Actions
The following table illustrates the Pedestrian Mobil...

Click here for full text