city of San Antonio


Some of our meetings have moved. View additional meetings.

File #: 18-1468   
Type: Capital Improvements
In control: City Council A Session
On agenda: 6/14/2018
Posting Language: Ordinance authorizing a Funding Agreement between the City of San Antonio and the San Antonio Botanical Society in the amount not-to-exceed $5,050,000.00 for the San Antonio Botanical Center Project, a 2017-2022 Bond Funded Project, located in Council District 2. [Peter Zanoni, Deputy City Manager; Mike Frisbie, Director, Transportation & Capital Improvements]
Attachments: 1. RFCA Map SA Botanical Center121817a, 2. Draft Ordinance, 3. Botanical Gardens - Partially Executed - 6-4-18, 4. Ordinance 2018-06-14-0435, 5. Staff Presentation
DEPARTMENT: Transportation & Capital Improvements


DEPARTMENT HEAD: Mike Frisbie, P.E.


COUNCIL DISTRICTS IMPACTED: Council District 2


SUBJECT:

Funding Agreement: San Antonio Botanical Center


SUMMARY:

An ordinance authorizing the execution of a Funding Agreement between the City of San Antonio and the San Antonio Botanical Society in the amount not-to-exceed $5,050,000.00, a 2017-2022 Bond Funded Project for the San Antonio Botanical Center, located in Council District 2.


BACKGROUND INFORMATION:

On May 6, 2017 the voters approved the 2017-2022 Bond Program, which authorized $5,050,000.00 for the San Antonio Botanical Center. These funds will be used towards Phase 2 improvements that would align with the San Antonio Botanical Center Master Plan. San Antonio Botanical Center provides education and hosts events for the public.

Phase 1 of the San Antonio Botanical Center Master Plan included $1,200,000.00 from the 2012 Bond Program and $9,100,001.00 raised by San Antonio Botanical Garden Society, Inc., which funded a parking garden, welcome and discovery garden, entry display garden, culinary garden, gift shop, outdoor kitchen, and the Family Adventure Garden. Construction was completed in October 2017.

Phase 2 improvements will include a new Education and Event Center with both an entry veranda and an event lawn veranda, an Event Lawn which will add outdoor space for events, a water wall fountain, and renovations to the Wisteria Arbor, which are existing columns and arbor that have wisteria growing up the columns and over the arches. Total cost of construction for this phase is estimated to cost $10,255,000, including the $5,050,000.00 funded from the 2017 Bond Program. The City's funding will be provided on a reimbursement basis, once the construction is verified and approved.

The project construction began in February 2018 with $5,205,000.00 already secured by San Antonio Botanical Society, Inc. and is estimated to be completed by Novem...