city of San Antonio


Some of our meetings have moved. View additional meetings.

File #: 19-5446   
Type: Capital Improvements
In control: City Council A Session
On agenda: 8/22/2019
Posting Language: Ordinance approving a construction contract to E-Z Bel Construction, LLC in the amount of $5,271,945.25 of which $1,191,094.95 will be reimbursed by San Antonio Water System (SAWS) and $198,797.80 will be reimbursed by CPS Energy for the South Pine Street/Greer Street Phase 1 Project, a 2017 Bond funded project. [Roderick Sanchez, Assistant City Manager; Razi Hosseini, Interim Director, Transportation & Capital Improvements]
Attachments: 1. Project Map_S. Pine and Greer, 2. Bid Summary_23-01636_Pine and Greer, 3. Draft Ordinance, 4. Staff Presentation, 5. Ordinance 2019-08-22-0652

DEPARTMENT: Transportation & Capital Improvements                     

 

 

DEPARTMENT HEAD: Razi Hosseini, P.E., R.P.L.S.                     

                     

 

COUNCIL DISTRICTS IMPACTED: 3

 

 

SUBJECT:

 

Contract Award:  South Pine Street/Greer Street Phase 1 (2017 Bond Project) 

 

 

SUMMARY:

 

An ordinance accepting the lowest responsive bid and awarding a construction contract to E-Z Bel Construction, LLC in the amount of $5,271,945.25 of which $1,191,094.95 will be reimbursed by San Antonio Water System (SAWS) and $198,797.80 will be reimbursed by CPS Energy for the South Pine Street/Greer Street Phase 1 Project, a 2017 Bond funded project, located in Council District 3. 

 

 

BACKGROUND INFORMATION:

 

Project Background

On May 6, 2017, voters approved the 2017 Bond Program which authorized $8,000,000.00 for drainage and flood control improvements for South Pine and Greer Street Phase 1 Project located in Council District 3.

 

The South Pine and Greer Street Phase 1 Project will provide for the construction of a storm drain system in the Highland Park area allowing flood relief to neighborhood streets and properties.  Construction of the system includes three underground storm drains out falling into existing systems at the South Pine Street and I-37 frontage intersection, the Topeka Boulevard and I-37 frontage intersection and the Greer Street and Hackberry Street intersection.  The project will also provide for the full-depth pavement reconstruction of Greer Street from Hackberry Street to South Pine Street, South Pine Street from Greer Street to I-37 frontage road and Topeka Boulevard from I-37 frontage road to Pine Street including curbs, sidewalks, driveway approaches and utility improvements.

 

Project construction is anticipated to begin in September 2019 and estimated to be completed by September 2020.

 

Procurement of Services

This project was advertised June 12, 2019 for construction bids in the San Antonio Hart Beat, on the City’s website, on the Texas Electronic State Business Daily, on TVSA, through the electronic bidding site CIVCAST and through the TCI Small Business Office.  Bids were opened on July 9, 2019 and two (2) bids were received.  Of these, E-Z Bel Construction, LLC submitted the lowest responsive bid.  A matrix of the bid outcome is included herein.

 

This contract will be awarded in compliance with the new Small Business Economic Development Advocacy (SBEDA) Program, which requires contracts to be reviewed by a Goal Setting Committee to establish a requirement and/or incentive unique to the particular contract in an effort to maximize the amount of small, minority and women-owned business participation on the contract.  The Goal Setting Committee set a 31% Minority/Women Business Enterprise (M/WBE) subcontracting goal and a 4% African American Business Enterprise (AABE) subcontracting goal.  E-Z Bel Construction, LLC has committed to meeting the subcontractor participation goal.

 

This construction contract was developed utilizing the low bid process.  Therefore, a Contracts Disclosure Form is not required.

 

 

ISSUE:

 

This ordinance accepts the lowest responsive bid and awards a construction contract to E-Z Bel Construction, LLC in the amount of $5,271,945.25 of which $1,191,094.95 will be reimbursed by San Antonio Water System (SAWS) and $198,797.80 will be reimbursed by CPS Energy for the South Pine Street/Greer Street Phase 1 Project, a 2017-2022 Bond funded project, located in Council District 3. 

 

The South Pine and Greer Street Phase 1 Project will provide for the construction of a storm drain system in the Highland Park area allowing flood relief to neighborhood streets and properties.  Construction of the system includes three underground storm drains out falling into existing systems at the South Pine Street and I-37 frontage intersection, the Topeka Boulevard and I-37 frontage intersection and the Greer Street and Hackberry Street intersection.  The project will also provide for the full-depth pavement reconstruction of Greer Street from Hackberry Street to South Pine Street, South Pine Street from Greer Street to I-37 frontage road and Topeka Boulevard from I-37 frontage road to Pine Street including curbs, sidewalks, driveway approaches and utility improvements.

 

Project construction is anticipated to begin in September 2019 and estimated to be completed by September 2020.

 

 

ALTERNATIVES:

 

As an alternative, City Council could choose not to award this contract and require staff to re-advertise this project.  Considering the additional time required for another solicitation process, this would adversely affect the timely completion of the project.

 

 

FISCAL IMPACT:

 

This is a one-time capital improvement expenditure in the amount of $5,271,945.25, authorized payable to E-Z Bel Construction, LLC of which $1,191,094.95 will be reimbursed by San Antonio Water System (SAWS) and $198,797.80 will be reimbursed by CPS Energy for the South Pine Street/Greer Street Phase 1 Project.  Funds are available from the 2017 Bond Program and are included in the FY 2019- FY 2024 Capital Improvement Program Budget.

 

RECOMMENDATION:

 

Staff recommends approval of this ordinance accepting the lowest responsive bid and awarding a construction contract to E-Z Bel Construction, LLC in the amount of $5,271,945.25 of which $1,191,094.95 will be reimbursed by San Antonio Water System (SAWS) and $198,797.80 will be reimbursed by CPS Energy for the South Pine Street/Greer Street Phase 1 Project.