city of San Antonio


Some of our meetings have moved. View additional meetings.

File #: 19-7088   
Type: Procedural
In control: City Council A Session
On agenda: 11/14/2019
Posting Language: Approving the following items related to the Avenue B and N. Alamo Bike Lane and Broadway Lower Segment - East Houston Street to IH-35 projects: [Roderick Sanchez, Assistant City Manager; Razi Hosseini, Interim Director, Transportation & Capital Improvements]
Attachments: 1. Map_AveBand Alamo_2019-09-16, 2. T31 Midtown Board Meeting Resolution__9.13.2019 FINAL, 3. Amendment_Sundt Design Build for Broadway_Ave B 10.31.19, 4. Draft Ordinance - Part A, 5. Draft Ordinance - Part B
Related files: 19-8416, 19-8417
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
DEPARTMENT: Transportation & Capital Improvements


DEPARTMENT HEAD: Razi Hosseini, P.E., R.P.L.S.


COUNCIL DISTRICTS IMPACTED: Council District 1


SUBJECT:

Funding Agreement for the Avenue B and N Alamo Bike Lane Project and Contract Amendment for the Broadway Lower Segment - East Houston Street to IH-35 Project


DEPARTMENT: Transportation & Capital Improvements


DEPARTMENT HEAD: Razi Hosseini, P.E., R.P.L.S.


COUNCIL DISTRICTS IMPACTED: Council District 1


SUBJECT:

Funding Agreement for the Avenue B and N. Alamo Bike Lane Project and Contract Amendment for the Broadway Lower Segment - East Houston Street to IH-35 Project


SUMMARY:

Consideration of the following items related to the Avenue B and N. Alamo Bike Lane and Broadway Lower Segment - East Houston Street to IH-35 projects:

A. An ordinance authorizing the execution of a Funding Agreement with the Midtown Board of Directors of Reinvestment Zone #31, granting up to $6,000,000.00 in reimbursable funds from Midtown Tax Increment Reinvestment Zone (TIRZ) #31 fund for the construction of the Avenue B and N Alamo Bike Lane Project located in Council District 1; and, authorizing the appropriation of these funds and amending of the FY 2020-2025 Capital Improvements Program with funds in the amount not to exceed $6,000,000.00 from Midtown Tax Increment Reinvestment Zone (TIRZ) #31 Fund for the Avenue B and N. Alamo Bike Lane Project.

B. An ordinance authorizing the execution of an amendment in the amount up to $6,000,000.00 to the 2017 Bond Broadway Corridor Lower Segment design-build contract with Sundt Construction, Inc. for the design and construction of Avenue B and N. Alamo bike lanes as part of the Broadway Lower Segment project.


BACKGROUND INFORMATION:

Project Background
On May 17, 2019, Transportation & Capital Improvements Department (TCI) staff, made a presentation to the Midtown TIRZ Board of Directors regarding the status of Broadway Corridor 2017 Bond project including the propo...