Posting Language: Ordinance approving a construction contract with D. Wilson Construction in an amount not to exceed $1,291,310.81 for the Airport Operations Area Perimeter Fence project at the San Antonio International Airport. Funding is budgeted and available from Interim Airport Financing. [Carlos Contreras, Assistant City Manager; Jesus Saenz, Director, Aviation]
Indexes: Aviation Contract
Attachments: 1. Graphic of project, 2. Draft Ordinance, 3. Intergration Agreement, 4. Ordinance 2020-02-13-0082, 5. Staff Presentation

DEPARTMENT: Aviation                     

 

 

DEPARTMENT HEAD: Jesus Saenz

                     

                     

COUNCIL DISTRICTS IMPACTED: Citywide

 

 

SUBJECT:

 

Construction Contract Award for Perimeter Fence Project at the San Antonio International Airport

 

 

SUMMARY:

 

Council consideration for an ordinance to award a construction contract to D. Wilson Construction, the lowest responsive bidder, in an amount not to exceed $1,291,310.81 for the Airport Operations Area Perimeter Fence project at the San Antonio International Airport. This project will remove and replace more than 15,300 feet of six-foot fencing with new eight-foot fencing. The project is funded from Interim Airport Financing.

 

 

BACKGROUND INFORMATION:

 

The current perimeter fence around the San Antonio International Airport includes segments that have been damaged from flooding and vehicular accidents. In 2018, the Aviation Department issued a task order to RS&H, one of the department’s on-call general engineering consultants, to assess the existing perimeter fence system for the Airport Operations Area (AOA). The assessment was to identify the current conditions of the fence and areas that are within or out of compliance of current security standards. The AOA fence refers to the perimeter fence that divides the public area with the secured area and does not include tenant-leased and other fencing. In 2019, RS&H recommended two areas that were within the available budget and are vulnerable to vehicular and animal intrusions.

 

The scope of this project will replace 15,355 feet of six-foot fencing in segments along Wetmore Road and Skyplace Blvd with new eight-foot fencing. This project includes the installation of additional buried mesh to deter wildlife onto the airfield. Any installed fencing that already meets the security requirements will be excluded from the project.

 

ISSUE:

 

The Invitation For Bids (IFB) was released on September 25, 2019. Eight bids were opened on October 29, 2019. After reviewing the bids, the Economic Development Department determined that the four lowest bidders were unresponsive due to non-compliance with the Small Business Economic Development Advocacy (SBEDA) Program. The four bidders did not meet the SBEDA goal nor did the firms submit a waiver as required by the SBEDA program. The fifth lowest bidder, D. Wilson Construction, did submit a waiver, which was granted by EDD. The bid by D. Wilson was analyzed and determined to be the lowest responsive bid.

 

 

ALTERNATIVES:

 

As an alternative, City Council could choose not to award this contract and require staff to re-advertise this project; however, re-advertising the project does not guarantee a lower bid and considering the additional time required for another solicitation process would adversely affect the timely completion of the project.

 

 

FISCAL IMPACT:

 

This is one-time capital improvement expenditure in the amount not to exceed $1,291,310.81 payable to D. Wilson Construction. Funds are available from Interim Airport Financing and are included in the FY 2020 - FY 2025 Capital Improvement Program.

 

 

RECOMMENDATION:

 

Staff recommends the award of a construction contract to D. Wilson Construction for the Airport Operations Area Perimeter Fence project at the San Antonio International Airport.