File #: 20-2627   
Type: Capital Improvements
In control: City Council A Session
On agenda: 5/7/2020
Posting Language: Ordinance approving the execution of an amendment in the increased amount not to exceed $157,694.00 to the $1,376,253.40 Civil Engineering Design Services Agreement with Lockwood, Andrews & Newman, Inc. for additional design services relating to the North Main Avenue and Soledad Street (Pecan Street to Navarro Street) Project, a 2017 Bond funded project located in Council District 1. Funding is included in the FY 2020 - FY 2025 Capital Improvement Program. [Roderick Sanchez, Assistant City Manager; Razi Hosseini, Director, Public Works]
Attachments: 1. Project Map - N. Main & Soledad, 2. Amendment - N. Main & Soledad Lockwood Civil Engineering FINAL, 3. Draft Ordinance, 4. Ordinance 2020-05-07-0308
DEPARTMENT: Public Works


DEPARTMENT HEAD: Razi Hosseini, P.E., R.P.L.S.


COUNCIL DISTRICTS IMPACTED: Council District 1


SUBJECT:

Civil Engineering Design Services Agreement Amendment: North Main Avenue & Soledad Street (Pecan Street to Navarro Street) Project (2017 Bond Project)


SUMMARY:

An ordinance approving the execution of an amendment in the increased amount not to exceed $157,694.00 to the $1,376,253.40 Civil Engineering Design Services Agreement with Lockwood, Andrews & Newman, Inc. for additional design services relating to the North Main Avenue and Soledad Street (Pecan Street to Navarro Street) Project, a 2017 Bond funded project located in Council District 1. Funds are available from 2017 General Obligation Bond Program and are included in FY 2020 - FY 2025 Capital Improvement Program.


BACKGROUND INFORMATION:

Project Background
On May 6, 2017, voters approved the 2017 Bond Program, which authorized $9,000,000.00 for North Main Avenue and Soledad Street (Pecan Street to Navarro Street) project, located in Council District 1. This project will provide for the reconstruction of North Main Avenue and Soledad Street from Pecan Street to Navarro Street including the construction of pedestrian amenities and enhancements as appropriate and within available funding. This project is a continuation of a 2012 Bond funded project, which converted North Main Avenue and Soledad Street to a two-way street and included various street and sidewalk improvements along North Main Avenue and Soledad Street between Commerce Street and Pecan Street.

Previous Council Action
On October 5, 2017, City Council approved a Civil Engineering Design Services Agreement with Lockwood, Andrews & Newman, Inc. in an amount not to exceed $1,376,253.40 for the design and construction phase services for North Main Avenue and Soledad Street (Pecan Street to Navarro Street) Project through Ordinance 2017-10-05-0742. The proposed amendment for additional design services wi...