city of San Antonio


Some of our meetings have moved. View additional meetings.

File #: 20-3378   
Type: Miscellaneous Item
In control: City Council A Session
On agenda: 6/11/2020
Posting Language: Ordinance approving a Joint Use Agreement with the San Antonio Water System to assist in the completion of the W-6 Upper Segment: Highway 90 to SW Military Drive Sewer Main Project; accepting an amount of $276,726.00 for the permanent and temporary use of City property at Nelson W. Wolff Municipal Stadium; and approving disbursement to the San Antonio Missions Baseball Club Inc. of $25,000.00 at the end of each of the next three played seasons, for a total up to $75,000.00, to offset parking revenue loss. The agreement will extend for three years beginning in July 2020. [Carlos Contreras, Assistant City Manager; Patricia Muzquiz Cantor, Director, Convention and Sports Facilities]
Attachments: 1. Map and diagram, 2. Agreement, 3. Filed Notes, 4. Draft Ordinance, 5. SAWS Joint Use Agreement (SAWS executed), 6. Ordinance 2020-06-11-0403
DEPARTMENT: Convention & Sports Facilities


DEPARTMENT HEAD: Patricia Muzquiz Cantor


COUNCIL DISTRICTS IMPACTED: Citywide


SUBJECT: Joint Use Agreement: SAWS use of City-owned property


SUMMARY:
This Ordinance authorizes a Joint Use Agreement between the City of San Antonio (CoSA) and the San Antonio Water System (SAWS) that will assist in the completion of the W-6 Upper Segment: Highway 90 to SW Military Drive Sewer Main Project and accepts an amount of $276,726.00 for the permanent and temporary use of CoSA property at Nelson W. Wolff Municipal Stadium property. The agreement will extend for three years beginning in July 2020. This ordinance also authorizes disbursement to the San Antonio Missions Baseball Club Inc. in the amount of $25,000.00 at the end of each played season for three years for a total of up to $75,000.00 to offset parking revenue loss.

BACKGROUND INFORMATION:
As part of the July 23, 2013 Consent Decree between the San Antonio Water System (SAWS) and the Environmental Protection Agency (EPA), SAWS will be addressing capacity constraints in the western sewer shed of San Antonio. The W-6 Upper Segment Sewer Main Project, a SAWS capital project, will replace and upsize approximately five miles of 54-inch pipe currently running through Lackland Air Force Base with a new 104-inch sewer main. The extent of this segment runs through both Districts 4 and 6 from a point just south of Southwest Military Drive near Leon Creek and just east of Old Pearsall Road, to a point near the intersection of Highway 90 and Callaghan Road.

In order to complete their project SAWS requires the temporary and joint use of CoSA-owned property, specifically 2.63 total acres on the south portion of the Nelson W. Wolff Municipal Stadium property. This ordinance would allow 1.5387 acres of the 2.63 to be used on a permanent basis with the remaining acreage being used temporarily during construction. Most of the construction will take place along the north side of H...

Click here for full text