File #: 20-4056   
Type: Capital Improvements
In control: City Council A Session
On agenda: 8/13/2020
Posting Language: Ordinance approving a construction contract to Pronto Sandblasting and Coating and Oil-Field Company, Inc. in the amount of $1,254,979.50 of which $367,191.00 will be reimbursed by San Antonio Water System (SAWS) for the District 5 Drainage Improvements (W. Gerald Avenue) project, a previously authorized debt funded project, located in Council District 5. Funds are available from previously authorized debt proceeds and are included in the FY 2020 - FY 2025 Capital Improvement Program. [Roderick Sanchez, Assistant City Manager; Razi Hosseini, Director, Public Works]
Attachments: 1. Project Map, 2. CivCast Bid Summary_District 5 Drainage, 3. Ordinance 2020-08-13-0518
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
DEPARTMENT: Public Works


DEPARTMENT HEAD: Razi Hosseini, P.E., R.P.L.S.


COUNCIL DISTRICTS IMPACTED: Council District 5


SUBJECT:

Contract Award: District 5 Drainage Improvements (W. Gerald Avenue)


SUMMARY:

An ordinance accepting the lowest responsive bid and awarding a construction contract to Pronto Sandblasting and Coating and Oil-Field Company, Inc. in the amount of $1,254,979.50 of which $367,191.00 will be reimbursed by San Antonio Water System (SAWS) for the District 5 Drainage Improvements (W. Gerald Avenue) project, a previously authorized debt funded project, located in Council District 5. Funds are available from previously authorized debt proceeds and are included in the FY 2020 - FY 2025 Capital Improvement Program.


BACKGROUND INFORMATION:

Project Background
As part of the City's FY 2018 Adopted Budget, $1,365,000.00 was approved for drainage improvements including street reconstruction and sidewalks for the District 5 Drainage Improvements (W. Gerald Avenue) project located in Council District 5.

Area residents have expressed concerns about localized drainage issues and the length of time storm runoff remains on W. Gerald Avenue. This project will provide for the construction of an underground storm drain system at W. Gerald Avenue from Somerset Road to 963 feet west of Somerset Road allowing flood relief to the street and surrounding neighborhood. Project construction is anticipated to begin in September 2020 and estimated to be completed in February 2021.

Procurement of Services
This project was advertised on June 3, 2020 for construction bids in the San Antonio Hart Beat, on the City's website, on the Texas Electronic State Business Daily, on TVSA and through the electronic bidding site CivCast website. Bids were opened on June 30, 2020 and eight (8) bids were received. Of these, Pronto Sandblasting and Coating and Oil-Field Company, Inc. submitted the lowest responsive bid. A matrix of the bid outcome is included herein.

Thi...