city of San Antonio


Some of our meetings have moved. View additional meetings.

File #: 20-3588   
Type: Staff Briefing - Without Ordinance
In control: Audit and Accountability Committee
On agenda: 8/18/2020
Posting Language: River Walk Improvements Phase 6 [Roderick Sanchez, Assistant City Manager; Razi Hosseini, Director, Public Works]
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
CITY OF SAN ANTONIO
PUBLIC WORKS DEPARTMENT
Interdepartmental Correspondence

TO: Erik Walsh, City Manager

FROM: Razi Hosseini, P.E., R.P.L.S., Director, Public Works

COPIES: Audit and Accountability Committee; Ben Gorzell, CPA, Chief Financial Officer; Kevin Barthold, City Auditor; Roderick J. Sanchez, AICP, CBO, Assistant City Manager; Lori Houston, Assistant City Manager; Luis Maltos, P.E., Interim Assistant Director, Public Works; John Jacks, Director, CCDO; Troy Elliott, CPA, Deputy Chief Financial Officer

SUBJECT: Consideration of Completed High Profile Solicitation

DATE: August 18, 2020

The following high profile project has completed the solicitation process. This item is presented to the Audit and Accountability Committee for review prior to the full City Council for consideration.

River Walk Improvements - Phase 6 (Public Works) - Department issued a Request for Competitive Sealed Proposals for improvements to several sections along the River Walk's historic river bend and river extension to complete the scope of work as outlined in the City's River Walk Master Plan. The scope of work includes upgrades to existing walks, walls, handrails and steps, electrical work and lighting fixtures, as well as upgrades to the streetcar station elevator.

Solicitation Type: Request for Competitive Sealed Proposals
Contracts Value: $3 Million
Term of Contract: Until Project Completion (estimated September 2021)
Number of Respondents:|910|Contracts to be Awarded:|910|Council Consideration: August 20, 2020
Evaluation Criteria: Experience, Background, Qualifications of Firm, Key Personnel, and Key Sub-Consultant: 25 points
Understanding of the Project, Construction Management Plan, and Work Sequence Plan: 25 points
Experience with San Antonio Region issues and past experience with the City of San Antonio: 10 points
Price Proposal: 20 points
SBE Prime Contract Program: 10 points
M/WBE Prime Contract Program: 10 points
SBEDA Requirements: 24% M/WBE and...

Click here for full text