city of San Antonio


Some of our meetings have moved. View additional meetings.

File #: 20-3588   
Type: Staff Briefing - Without Ordinance
In control: Audit and Accountability Committee
On agenda: 8/18/2020
Posting Language: River Walk Improvements Phase 6 [Roderick Sanchez, Assistant City Manager; Razi Hosseini, Director, Public Works]
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

CITY OF SAN ANTONIO

PUBLIC WORKS DEPARTMENT

Interdepartmental Correspondence

 

TO:                                          Erik Walsh, City Manager

 

FROM:                     Razi Hosseini, P.E., R.P.L.S., Director, Public Works

 

COPIES:                     Audit and Accountability Committee; Ben Gorzell, CPA, Chief Financial Officer; Kevin Barthold, City Auditor; Roderick J. Sanchez, AICP, CBO, Assistant City Manager; Lori Houston, Assistant City Manager; Luis Maltos, P.E., Interim Assistant Director, Public Works; John Jacks, Director, CCDO; Troy Elliott, CPA, Deputy Chief Financial Officer

 

SUBJECT:                     Consideration of Completed High Profile Solicitation

 

DATE:                     August 18, 2020

 

The following high profile project has completed the solicitation process. This item is presented to the Audit and Accountability Committee for review prior to the full City Council for consideration.

 

River Walk Improvements - Phase 6 (Public Works) - Department issued a Request for Competitive Sealed Proposals for improvements to several sections along the River Walk’s historic river bend and river extension to complete the scope of work as outlined in the City’s River Walk Master Plan.  The scope of work includes upgrades to existing walks, walls, handrails and steps, electrical work and lighting fixtures, as well as upgrades to the streetcar station elevator.

 

Solicitation Type:                                          Request for Competitive Sealed Proposals

Contracts Value:                                          $3 Million

Term of Contract:                                          Until Project Completion (estimated September 2021)

Number of Respondents:                     2

Contracts to be Awarded:                     1

Council Consideration:                     August 20, 2020

Evaluation Criteria:                     Experience, Background, Qualifications of Firm, Key Personnel, and Key Sub-Consultant: 25 points

Understanding of the Project, Construction Management Plan, and Work Sequence Plan: 25 points

                     Experience with San Antonio Region issues and past experience with the City of San Antonio:  10 points

                     Price Proposal:  20 points

                     SBE Prime Contract Program:   10 points

                     M/WBE Prime Contract Program:  10 points

SBEDA Requirements:                     24% M/WBE and 3% AABE Subcontracting Requirement

Local Preference Program:                     Not Applicable

Veteran Owned Small Business Preference Program: Not Applicable

Voting Members:                                          Lori Houston, Assistant City Manager, City Manager’s Office

Veronica Carrillo, Assistant Director, Center City Development & Operations

Lincoln St. George, River Walk Operations Manager, Center City Development & Operations

Maggie Thompson, Executive Director, San Antonio River Walk Association

Gopinath Akalkotkar, City Architect, Public Works Department

 

 

Due diligence conducted for the respondents to the above solicitation included a search of federal and state debarment lists, prohibited political contributions, conflicts of interest, delinquent City/County taxes, outstanding payments to the City, payment of state franchise fees as well as a search of the internet for pertinent business information. No material findings were noted that would prevent the City from awarding to the selected vendor.

 

Staff recommends committee approval to proceed with scheduling this item for full City Council consideration.