city of San Antonio


Some of our meetings have moved. View additional meetings.

File #: 20-4412   
Type: Procedural
In control: City Council A Session
On agenda: 12/3/2020
Posting Language: Approving the following two items related to the Auldine Drive & Burr Oak Drive (Alley to Outfall) project, a 2017 Bond and Storm Water Operating funded drainage project located in Council District 9: [Roderick Sanchez, Assistant City Manager; Razi Hosseini, Director, Public Works]
Attachments: 1. Map_Auldine and Burr Oak, 2. Bid Results _Civcast, 3. Draft Ordinance A, 4. Draft Ordinance B
Related files: 20-7037, 20-7036
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
DEPARTMENT: Public Works


DEPARTMENT HEAD: Razi Hosseini, P.E., R.P.L.S.


COUNCIL DISTRICTS IMPACTED: Council District 9


SUBJECT:

Contract Award & Deductive Change Order: Auldine Drive & Burr Oak Drive (Alley to Outfall) (2017 Bond Project)


SUMMARY:

Consideration of the following items related to the Auldine Drive & Burr Oak Drive (Alley to Outfall) project, a 2017 Bond and Storm Water Operating funded drainage project, located in Council District 9:

A. An ordinance accepting the lowest responsive bid and awarding a construction contract including an additive alternate to Clearfield Construction, LLC in the amount of $3,076,644.60 of which $372,650.10 will be reimbursed by San Antonio Water System and $227,770.00 will be reimbursed by CPS Energy for the Auldine Drive & Burr Oak Drive (Alley to Outfall) project, a 2017 Bond and Storm Water Operating funded drainage project, located in Council District 9. Funds are available from the 2017 - 2022 General Obligation Bond Program and the Storm Water Operating Fund and are included in the FY 2021 - FY 2026 Capital Improvement Program.

B. An ordinance approving a City requested deductive change order in the decreased amount of $275,804.00 for a revised total contract amount of $2,800,840.60 with Clearfield Construction, LLC for the Auldine Drive & Burr Oak Drive (Alley to Outfall) project, a 2017 Bond and Storm Water Operating funded drainage project, located in Council District 9.


BACKGROUND INFORMATION:

Project Background
On May 6, 2017, voters approved the 2017 Bond Program which authorized $2,800,000.00 for drainage improvements for the Auldine Drive & Burr Oak Drive (Alley to Outfall) project located in Council District 9. As part of the adopted FY 2020 budget, Storm Water Operating funds in the amount of $701,000.00 were approved for this project. The project will provide for the reconstruction of the alleyway between Auldine Drive and Burr Oak Drive including improvements to the existing st...