city of San Antonio


Some of our meetings have moved. View additional meetings.

File #: 20-7037   
Type: Capital Improvements
In control: City Council A Session
On agenda: 12/3/2020
Posting Language: Ordinance approving a City requested deductive change order in the decreased amount of $275,804.00 for a revised total contract amount of $2,800,840.60 with Clearfield Construction, LLC for the Auldine Drive & Burr Oak Drive (Alley to Outfall) project, a 2017 Bond and Storm Water Operating funded drainage project.
Attachments: 1. Map_Auldine and Burr Oak, 2. Bid Results _Civcast, 3. Ordinance 2020-12-03-0845
Related files: 20-4412, 20-7036
DEPARTMENT: Public Works


DEPARTMENT HEAD: Razi Hosseini, P.E., R.P.L.S.


COUNCIL DISTRICTS IMPACTED: Council District 9


SUBJECT:

Contract Award & Deductive Change Order: Auldine Drive & Burr Oak Drive (Alley to Outfall) (2017 Bond Project)


SUMMARY:

Consideration of the following items related to the Auldine Drive & Burr Oak Drive (Alley to Outfall) project, a 2017 Bond and Storm Water Operating funded drainage project, located in Council District 9:

A. An ordinance accepting the lowest responsive bid and awarding a construction contract including an additive alternate to Clearfield Construction, LLC in the amount of $3,076,644.60 of which $372,650.10 will be reimbursed by San Antonio Water System and $227,770.00 will be reimbursed by CPS Energy for the Auldine Drive & Burr Oak Drive (Alley to Outfall) project, a 2017 Bond and Storm Water Operating funded drainage project, located in Council District 9. Funds are available from the 2017 - 2022 General Obligation Bond Program and the Storm Water Operating Fund and are included in the FY 2021 - FY 2026 Capital Improvement Program.

B. An ordinance approving a City requested deductive change order in the decreased amount of $275,804.00 for a revised total contract amount of $2,800,840.60 with Clearfield Construction, LLC for the Auldine Drive & Burr Oak Drive (Alley to Outfall) project, a 2017 Bond and Storm Water Operating funded drainage project, located in Council District 9.


BACKGROUND INFORMATION:

Project Background
On May 6, 2017, voters approved the 2017 Bond Program which authorized $2,800,000.00 for drainage improvements for the Auldine Drive & Burr Oak Drive (Alley to Outfall) project located in Council District 9. As part of the adopted FY 2020 budget, Storm Water Operating funds in the amount of $701,000.00 were approved for this project. The project will provide for the reconstruction of the alleyway between Auldine Drive and Burr Oak Drive including improvements to the existing st...

Click here for full text