DEPARTMENT: Public Works
DEPARTMENT HEAD: Razi Hosseini P.E., R.P.L.S
COUNCIL DISTRICTS IMPACTED: Citywide
SUBJECT:
Contract Award: FY 2021 Neighborhood Access and Mobility Program and Infrastructure Management Program (Packages 1-3)
SUMMARY:
Consideration of the following four construction contracts totaling $6,151,065.92 to complete sidewalk repairs associated with the Neighborhood Access and Mobility Program (NAMP) and Infrastructure Management Program (IMP):
A. An ordinance accepting the lowest responsive bid and awarding the FY 2021 Wheelchair Ramp Installation Task Order Contract Package 1 to Garren Construction, LLC in an amount not to exceed $524,096.22.
B. An ordinance accepting the lowest responsive bid and awarding the FY 2021 Flatwork and Street Improvements Task Order Contract Package 1 to San Antonio Concepts Construction, LLC in an amount not to exceed $2,809,877.10 of which $121,300.00 will be reimbursed by San Antonio Water System (SAWS) and $175.00 will be reimbursed by CPS Energy for necessary adjustments to their existing infrastructure.
C. An ordinance accepting the lowest responsive bid and awarding the FY 2021 Flatwork and Street Improvements Task Order Contract Package 2 to NBM Development, Inc. in an amount not to exceed $1,411,919.10 of which $58,750.00 will be reimbursed by San Antonio Water System (SAWS) and $1,000.00 will be reimbursed by CPS Energy for necessary adjustments to their existing infrastructure.
D. An ordinance accepting the lowest responsive bid and awarding the FY 2021 Flatwork and Street Improvements Task Order Contract Package 3 to NBM Development, Inc. in an amount not to exceed $1,405,173.50 of which $58,750.00 will be reimbursed by San Antonio Water System (SAWS) and $1,000.00 will be reimbursed by CPS Energy for necessary adjustments to their existing infrastructure.
BACKGROUND INFORMATION:
Project Background
During the FY 2021 Budget process, City Council approved $2.2 million for the NAMP Pr...
Click here for full text