Contract Award: FY 2021 Pavement Preservation Package 3 - Base Repair Task Order Contract
SUMMARY:
An ordinance accepting the lowest responsive bid and awarding the FY 2021 Pavement Preservation Package 3 - Base Repair Task Order Contract to J&P Paving Co, Inc. in an amount not to exceed $892,632.25 of which $11,625.00 will be reimbursed by San Antonio Water System (SAWS) and $3,375.00 will be reimbursed by CPS Energy for necessary adjustments to their existing infrastructure related to street maintenance pavement preservation projects identified in the Infrastructure Management Program.
BACKGROUND INFORMATION:
Project Background
With the adoption of the FY 2021 Budget on September 17, 2020, City Council approved a $102 million Street Maintenance Program (SMP) budget, comprised of both $12 million in-house and $90 million contractual street maintenance projects. The FY 2021 SMP includes 282 Street Maintenance projects totaling $43 million, deferred from FY 2020 as a result of financial impacts of COVID 19; and, $59 million in new projects encompassing 935 SMP projects.
This ordinance authorizes a contract totaling $892,632.25 for the construction of the FY 2021 Street Maintenance Pavement Preservation Projects. Additional contracts are scheduled to be awarded at a later date for the remaining pavement preservation SMP projects.
Procurement of Services
FY 2021 Pavement Preservation Package 3 - Base Repair Task Order Contract was advertised for construction bids on October 14, 2020 in the San Antonio Hart Beat, the City's website, the Texas Electronic State Business Daily, on TVSA and through the electronic bidding website CIVCAST. Bids for the FY 2021 Pavement Preservation Package 3 - Base Repair Task Order Contract were due on November 17, 2020 and six (6) responsive bids were received. J&P Paving Co, Inc. was the lowest...