city of San Antonio


Some of our meetings have moved. View additional meetings.

File #: 21-2113   
Type: Miscellaneous Item
In control: City Council A Session
On agenda: 4/1/2021
Posting Language: Ordinance approving a Development Agreement between the Northeast Corridor TIRZ Board of Directors, Bitterblue, Inc., and the City of San Antonio for eligible public improvements for an amount not to exceed $1,650,000 reimbursed over three fiscal years (FY 2021-FY 2023) for the David Edwards Drive Extension Project. [Lori Houston, Assistant City Manager; VerĂ³nica R. Soto, FAICP, Director, Neighborhood and Housing Services]
Attachments: 1. Agreement, 2. Longhorn Quarry Site Plan, 3. Draft Ordinance, 4. Ordinance 2021-04-01-0216
Related files: 21-2892, 21-2882
DEPARTMENT: Neighborhood and Housing Services Department


DEPARTMENT HEAD: Ver?nica R. Soto, FAICP, Director


COUNCIL DISTRICTS IMPACTED: 10


SUBJECT:

An Ordinance approving the execution of a Development Agreement between the Northeast Corridor TIRZ Board of Directors, Bitterblue, Inc., and the City of San Antonio for eligible public improvements for an amount not to exceed $1,650,000 reimbursed over three fiscal years (FY 2021-FY 2023) for the David Edwards Drive Extension Project in Council District 10.

SUMMARY:

The Longhorn Quarry redevelopment is a master planned community designed to be transformed into a hub for living spaces, businesses, leisure, and culture. The total cost of the redevelopment is approximately $100 million. The extension of David Edward Drive to Schertz Road will spur further development within the Longhorn Quarry to include a proposed high school of Science and Technology and a multi-family apartment project. The street extension will act as a stent for the heart and success of the Longhorn Quarry Master Development, sparking interest in construction of remaining parcels for retail, commercial, and multifamily projects.

The project consists of the construction and delivery of new public infrastructure, including street design and construction of an extension of David Edwards Drive. The public improvements associated with extending David Edwards Drive include, sidewalks, streetlights, monument signs, street signs, drainage, curb cuts, utilities, sitework, and landscaping. The project is anticipated to begin in April 2021 and be completed in December 2021.

BACKGROUND INFORMATION:

On February 9, 2021 the Northeast Corridor TIRZ Board of Directors approved a Development Agreement with Bitterblue, Inc. for eligible public improvements for an amount not to exceed $1,650,000 reimbursed over three fiscal years (FY 2021-FY 2023).

The Longhorn Quarry is a master-planned redevelopment comprising of more than 100,000 sf of comme...