File #: 14-571   
Type: Purchase of Services
In control: City Council A Session
On agenda: 4/10/2014
Posting Language: An Ordinance accepting the bid from Dorazio Enterprises, Inc. to repair San Antonio River tunnel outlet gates and replace the tunnel inlet transfer switch for a total cost of $76,000.00, from the FY 2014 Storm Water Operations Fund. [Ben Gorzell, Chief Financial Officer; Troy Elliott, Director, Finance]
Attachments: 1. Invitation for Bid - Dorazio Enterprises, Inc., 2. 6100003885 Bid Tab, 3. Draft Ordinance, 4. Ordinance 2014-04-10-0223
DEPARTMENT: Finance


DEPARTMENT HEAD: Troy Elliott


COUNCIL DISTRICTS IMPACTED: All


SUBJECT:
San Antonio River Outlet Tunnel Gate Repair and Transfer Switch Replacement


SUMMARY:
This ordinance authorizes a contract with Dorazio Enterprises, Inc. to repair the San Antonio River tunnel outlet gates and replace the tunnel inlet transfer switch for a total cost of $76,000.00. Funding is available from the FY 2014 Storm Water Operations Fund.


BACKGROUND INFORMATION:
Submitted for City Council consideration and action is the attached bid tabulation of two competitive bids to provide repairs to the San Antonio River tunnel outlet gates and replacement of the tunnel inlet transfer switch. During a flood on May 25, 2013, the gates and transfer switch received severe damage from the force of the volume of storm water run-off.

Funding for repair was approved in the FY 2014 Budget and a solicitation was released in November 2013. During the bid period a site visit revealed that the existing automated transfer switch (ATS) was obsolete and specifications would need to include engineering a new model ATS to retrofit in existing system panel. As a result, the bid was cancelled and re-issued in December 2013 with updated specifications. The Invitation for Bid (IFB) was evaluated base on the published bid specifications and the low bid was submitted by Dorazio Enterprises, Inc.

The repair to the tunnel outlet gates and replacement of the transfer switch are covered by a minimum one year warranty of all components parts and service.


ISSUE:
This contract will provide the Transportation and Capital Improvements Department with repairs required for the San Antonio River tunnel outlet gate and replacement of the tunnel inlet transfer switch.

This contract is within the scope of the Small Business Economic Development Advocacy (SBEDA) Program. However, due to the type of commodities/services being procured and value of the contract,...