File #: 15-1270   
Type: Capital Improvements
In control: City Council A Session
On agenda: 3/12/2015
Posting Language: An Ordinance for Quail Creek Tributary Drainage, a 2012-2017 Bond funded project, located in Council District 10, accepting the lowest responsive bid and awarding a construction contract to Capital Excavation Company in an amount not to exceed $2,099,290.15 of which $460,226.65 will be reimbursed by San Antonio Water Systems and $17,955.00 will be reimbursed by CPS Energy. [Peter Zanoni, Deputy City Manager; Mike Frisbie, Director, Transportation & Capital Improvements]
Attachments: 1. Quail Creek Tributary A Drainage - Summary Bid Tabs.pdf, 2. QuailCreek_RFCAMap.pdf, 3. Draft Ordinance, 4. Ordinance 2015-03-12-0184
DEPARTMENT: Transportation & Capital Improvements

DEPARTMENT HEAD: Mike Frisbie

COUNCIL DISTRICT(S) IMPACTED: 10

SUBJECT: Contract Award: Quail Creek Tributary Drainage

SUMMARY:
An ordinance for Quail Creek Tributary Drainage, a 2012-2017 Bond Program project, located in Council District 10, accepting the lowest responsive bid and awarding a construction contract to Capital Excavation Company (Capital Excavation) in amount not to exceed $2,099,290.15 of which $460,226.65 will be reimbursed by San Antonio Water Systems (SAWS) and $17,955.00 will be reimbursed by CPS Energy.

BACKGROUND INFORMATION:
Project Background
The 2012-2017 General Obligation Bond Program authorized $4,949,000.00 for funding of the Quail Creek Drainage Project. The balance of the Project funds will be used for design services, environmental services, advertising and project management, with any remaining funds to be realized as bond savings.
This Project provides for improving the drainage in Quail Creek in the vicinity of Loop 410 and northward with channel and bridge improvements, which includes lowering the channel bottom and increasing the channel bottom width to keep a natural earthen channel, as well as, replacing the culvert crossing at Barrington with an open span bridge.
Public Meetings were held on June 4, 2014, at Hamilton Community Center Gym and on September 21, 2014 at the Church of Reconciliation. Project construction is anticipated to begin April 2015 and estimated to be completed by December 2015.
Procurement of Services
An Invitation for bids was advertised in the San Antonio Hart Beat, on the City's website, on the Texas Electronic State Business Daily, and through the TCI Small Business Office in December 2014. In addition, plans were available for review by potential bidders at the office of Atkins North America, Inc., 10100 Reunion Place, Suite 850, San Antonio, Texas 78216. Bids for this Project were opened on January 6, 2015 and four (4) bids ...