File #: 15-2294   
Type: Capital Improvements
In control: City Council A Session
On agenda: 5/7/2015
Posting Language: An Ordinance for the Yanaguana Garden Project related to the Hemisfair Park Project, a 2012-2017 General Obligation Bond funded Project, located in Council District 1 authorizing acceptance of a reimbursement to the City of San Antonio from the San Antonio Water System in the amount of $179,717.40 for the joint-bid of sewer and utility work. [Peter Zanoni, Deputy City Manager; Mike Frisbie, Director, Transportation and Capital Improvements]
Attachments: 1. Fiscal Impact Form_Hemisfair-Yanaguana Garden, 2. Ordinance 2015-05-07-0364
DEPARTMENT: Transportation & Capital Improvements


DEPARTMENT HEAD: Mike Frisbie, P.E.


COUNCIL DISTRICTS IMPACTED: Council District 1


SUBJECT: SAWS Reimbursement-Hemisfair Park-Yanaguana Garden Project



SUMMARY:

An ordinance authorizing a reimbursement to be received to the City of San Antonio from SAWS for the joint-bid of sewer and utility work associated in the construction of the Yanaguana Garden Project in the amount of $179,717.40 and related to the Hemisfair Park Project, a 2012-2017 General Obligation Bond funded Project, located in Council District 1.


BACKGROUND INFORMATION:

The voters approved 2012-2017 Bond Program which included four (4) projects totaling $15 million for Parks, Recreation and Open Space Improvements at HemisFair Park. The projects are: 1) Hemisfair Play Escape Project (Yanaguana Garden); 2) Magik Theatre Restoration; 3) Historic Homes and 4) The Civic Park. All are located within the HemisFair Park.

The Yanaguana Garden Project is being constructed to be high density play area within Hemisfair Park for people of all ages. Construction of the initial site work includes demolition of outdate and dilapidated park amenities and providing upgrades to the infrastructure necessary to support and accommodate the improvements for core framework of the project. Improvements such as open park space, plazas, climbing structures, water and sand play elements, new restrooms and a shaded promenade connecting these elements are part of the project.

A previously executed Construction Manager at Risk (CMR) contract with Joeris General Contractors, Ltd., for construction of Yanaguana Garden (HemisFair Play Escape Project) was approved by City Council on June 20, 2013 in the amount of $3,981,450.00, of which $179,717.40 will be reimbursed to the Project by SAWS for sewer and utilities work associated with the project. This scope of work was designed to be included in the Construction Manager at Risk constru...

Click here for full text