File #: 16-3006   
Type: Capital Improvements
In control: City Council A Session
On agenda: 6/2/2016
Posting Language: An Ordinance awarding the 2016 Infrastructure Management Program Sidewalk Projects Contract to Allbrite Constructors of Texas, Inc. in an amount not to exceed $1,150,532.95, for the construction of eight IMP sidewalk projects located throughout the City of which $27,367.50 will be reimbursed by San Antonio Water System for necessary adjustments to its existing infrastructure. [Peter Zanoni, Deputy City Manager; Mike Frisbie, Director, Transportation & Capital Improvements]
Attachments: 1. Bid Matrix - 2016 IMP Sidewalk Projects Contract, 2. BIDTAB2016IMPSidewalkProjectsContract, 3. Recommendation Letter Allbrite - 2016 IMP Sidewalk, 4. Allbrite Constructors1295, 5. Sidewalks Map, 6. Ordinance 2016-06-02-0389
DEPARTMENT: Transportation & Capital Improvements


DEPARTMENT HEAD: Mike Frisbie, P.E.


COUNCIL DISTRICTS IMPACTED: Citywide


SUBJECT:

2016 Infrastructure Management Program (IMP) Sidewalk Projects Contract

SUMMARY:

An ordinance awarding the 2016 Infrastructure Management Program (IMP) Sidewalk Projects Contract to Allbrite Constructors of Texas, Inc. in an amount not to exceed $1,150,532.95, for the construction of eight (8) IMP sidewalk projects located throughout the City of which $27,367.50 will be reimbursed by San Antonio Water System for necessary adjustments to its existing infrastructure.


BACKGROUND INFORMATION:

Project Background
During the FY 2016 Budget process, City Council approved $15 million to complete numerous sidewalk and pedestrian-related projects. As part of the department's continuing efforts to expedite project delivery and complete sidewalk and pedestrian-related projects citywide, the Transportation & Capital Improvements Department has solicited bids for construction services and will be utilizing various construction companies to complete the construction of several sidewalk-related projects.

This contract for sidewalk projects includes, but is not limited to, the construction of sidewalks, curbs, wheelchair ramps, retaining walls and any other work required for the completion of the assigned projects located throughout the City. SAWS' participation on these contracts is necessary in order to complete adjustments to its existing infrastructure within the project limits that impact City projects. SAWS will reimburse its improvement costs to the City of San Antonio, based on the bid unit prices received per these construction contracts.

The locations for these projects are listed below:

Location
Limits
Brookview
Dresden to Burwood
McCullough Ave
Harriett Dr to Oblate
Annarose Ln
Prairie Hill to Hunters Crk
Nw 19th St
W Martin St to W Commerce St
Holy Cross
Aurora Ave to Maria Elena
...

Click here for full text