Posting Language: An Ordinance authorizing a change order for the Theo Avenue and Malone Corridor Improvements Project, a 2012-2017 Bond funded project, in the amount of $282,394.88 and authorizing payment to Capital Excavation Company for curbs, sidewalks, driveway approaches and the resurfacing of pavement at the intersecting streets between Theo Avenue and Malone Avenue, located in Council District 5. [Peter Zanoni, Deputy City Manager; Mike Frisbie, Director, Transportation & Capital Improvements]
Attachments: 1. Theo-Malone Site Map (2), 2. Theo-Malone COU &1295 form, 3. Draft Ordinance, 4. Ordinance 2017-06-08-0419
DEPARTMENT: Transportation & Capital Improvements


DEPARTMENT HEAD: Mike Frisbie, P.E.


COUNCIL DISTRICT(S) IMPACTED: Council District 5

SUBJECT:

Change Order: Theo and Malone Corridors

SUMMARY:

An ordinance authorizing a change order for the Theo Avenue and Malone Corridor Improvements Project, a 2012-2017 Bond funded project, in the amount of $282,394.88 and authorizing payment to Capital Excavation Company for curbs, sidewalks, driveway approaches and pavement restoration at the intersecting streets between Theo Avenue and Malone Avenue located in Council District 5.

BACKGROUND INFORMATION:

The 2012-2017 General Obligation Bond Program authorized $14,195,000.00 for the Theo Avenue & Malone Avenue Corridors Project. On February 12, 2015, City Council authorized a construction award in the amount of $15,095,329.00 to Capital Excavation and of this amount $4,788,426.00 to be reimbursed by San Antonio Water Systems (SAWS) and $1,029,145.00 to be reimbursed by CPS Energy.

This Project provided for the reconstruction of approximately 1.25 miles of the one-way street Theo Avenue and 1.25 miles of the one-way street Malone Avenue from IH-35 to Zarzamora, including two 11-foot travel lanes, an 8-foot parking lane, a 5 foot bicycle lane, 4-foot sidewalks, curbs, driveway approaches and drainage improvements throughout the project limits. Traffic signal upgrades were included at the intersections of Nogalitos and Theo Avenue and Nogalitos and Malone Avenue. A community meeting was held on April 25, 2013 at the Palm Heights Park Community Center.

Project construction began in February 2015 and is currently in the final stages of construction with estimated completion in late June 2017.

Previous Council Action
A previously executed contract with Capital Excavation Company for the Theo and Malone Corridor Project, in the amount of $15,095,329.00, was approved by City Council on February 12, 2015 through Ordinance 2015-02-12-0085. A table of the subsequent cha...