Posting Language: Ordinance approving a construction contract to Garren Construction, in the amount $151,166.67 from Sales Tax Venue funds to install Howard W. Peak Vehicular Wayfinding Signs, included in the FY 2018-2023 Capital Improvement Program. [María D. Villagómez, Assistant City Manager; Xavier D. Urrutia, Director, Parks & Recreation]
Attachments: 1. Formal Invitation for Bid to Contract for Installation of Howard W. Peak Vehicular Wayfinding Signage 6-21-2018, 2. Exhibit 1 - Bid Tabulation for Installation of Howard W. Peak Vehicular Wayfinding Signage 6-21-2018, 3. Howard W. Peak Greenway Trails Vehicular Wayfinding Locations 6-21-2018, 4. Staff Presentation, 5. Draft Ordinance, 6. Ordinance 2018-06-21-0469
DEPARTMENT: Parks and Recreation


DEPARTMENT HEAD: Xavier D.Urrutia


COUNCIL DISTRICTS IMPACTED: City Wide


SUBJECT:

Construction Contract for Installation of Howard W. Peak Vehicular Wayfinding Signage


SUMMARY:

This ordinance accepts the lowest qualified bid, awards a construction contract to Garren Construction, and authorizes payment in the amount of $151,166.67 from 2015 Sales Tax Venue funds to install Howard W. Peak Vehicular Wayfinding Signs, and is included in the FY 2018-2023 Capital Improvement Program.


BACKGROUND INFORMATION:

A Vehicular Wayfinding Sign project is proposed to enhance the growing network of interconnected hike and bike trails now known as the Howard W. Peak Greenway Trails system, which is funded through sales tax initiatives approved by voters in 2000, 2005, 2010, and 2015. This newly added vehicular wayfinding signage will direct trail visitors to parking access locations from adjacent streets and intersections. There will be approximately 176 wayfinding signs at 72 locations along the Leon, Salado, and Medina River Greenway trails. These improvements will become unique additions to the municipal park system's creekways program for hiking, biking, and other recreational uses. The design work was performed by Terra Design Group.

The Request for Low Qualified Bids was advertised the third and fourth weeks of March and the first week of April 2018 in the Hart Beat, the Texas Electronic State Business Daily, the City's website, and announced on the City's public access station TVSA. Four (4) bids were received. After reviewing the bidders' qualifications and conducting interviews, Garren Construction was selected with the lowest qualified bid of $151,166.67. The lowest bid was deemed non-responsive due to an incomplete bid package. A standard construction contract will be executed and a summary of the bids is shown on Exhibit 1. Garren Construction has not previously performed City of San Antonio projects; however, t...