city of San Antonio


Some of our meetings have moved. View additional meetings.

File #: 18-5252   
Type: Capital Improvements
In control: City Council A Session
On agenda: 10/18/2018
Posting Language: Ordinance approving a change order for the Salado Creek Tributary "B" Channel Stabilization Project, a Storm Water Regional Facilities Funded $1,125,187.72 project, in the amount of $166,558.42 and approving payment to Curran Contracting Company to extend the drainage channel reconstruction limits by 200 feet to Pecan Valley Avenue, located in Council District 2. [Peter Zanoni, Deputy City Manager; Mike Frisbie, Director, Transportation & Capital Improvements]
Attachments: 1. Salado Creek Change Order Map, 2. Draft Ordinance, 3. Ordinance 2018-10-18-0823
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
DEPARTMENT: Transportation & Capital Improvements


DEPARTMENT HEAD: Mike Frisbie, P.E.


COUNCIL DISTRICTS IMPACTED: Council District 2


SUBJECT:

Change Order: Salado Creek Tributary "B" Channel Stabilization Project


SUMMARY:

An ordinance approving a change order in the amount of $166,558.42 and authorizing payment to Curran Contracting Company for the Salado Creek Tributary "B" Channel Stabilization Project, an authorized 2014 Storm Water Regional Facilities funded project located in Council District 2, to extend the drainage channel reconstruction limits by a total of 200 feet to Pecan Valley Avenue.

BACKGROUND INFORMATION:

Project Background
This is an 2014 Storm Water Regional Facilities Funded project. This project provides for the replacement and demolition of the existing concrete drainage channel with a new concrete lined channel approximately 1,800 feet in length from IH-10 to Pecan Valley Avenue. Project construction began in March 2018 and is estimated to be completed by November 2018.

Previous Council Action
A previously executed contract with Curran Contracting Company for Salado Creek Tributary "B" Channel Stabilization Project in the amount of $1,125,187.72 was approved by City Council on January 18, 2018 through Ordinance 2018-01-18-0016. There have been no previous Change Orders for this contract. This change order will increase the contract by $166,558.42, to a total of $1,291,746.14. This will be the first change order for this project.

The following table illustrates the change orders which have occurred since construction on this project began:
Item
Amount
Original Contract Value
$1,125,187.72
Proposed Change Order
$166,558.42
Revised Contract Value
$1,291,746.14


The Small Business Economic Development Advocacy (SBEDA) Program Goal Setting Committee set a 26% Minority/Women Business Enterprise (M/WBE) subcontracting goal and a 4% African American Business Enterprise (AABE) subc...

Click here for full text