Posting Language: Ordinance awarding a construction contract in the amount of $1,698,757.64 payable to Jerdon Enterprise, L.P. for the Buena Vista Corridor (Frio Street to Santa Rosa Street) Project, a 2012-2017 Bond funded Project, located in Council Districts 1 and 5. [Peter Zanoni, Deputy City Manager; Razi Hosseini, Interim Deputy Director]
Attachments: 1. Project Location Map, 2. Bid Summary_Buena Vista, 3. Draft Ordinance, 4. Ordinance 2019-04-11-0302, 5. Staff Presentation
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
DEPARTMENT: Transportation & Capital Improvements


DEPARTMENT HEAD: Razi Hosseini, P.E. R.P.L.S


COUNCIL DISTRICTS IMPACTED: Council Districts 1 & 5


SUBJECT:

Contract Award: Buena Vista Corridor (Frio Street to Santa Rosa Street) Project


SUMMARY:

An ordinance accepting the lowest responsive bid with one additive alternate and awarding a construction contract in the amount of $1,698,757.64 payable to Jerdon Enterprise, L.P for the Buena Vista Corridor (Frio Street to Santa Rosa Street) Project, a 2012-2017 Bond funded Project located in Council Districts 1 and 5.


BACKGROUND INFORMATION:

Project Background
The Buena Vista Corridor (Frio Street to Santa Rosa Street) Project is a $2,500,000.00 2012-2017 General Obligation Bond funded Project. The project will provide for improvements to the Buena Vista Corridor along Frio Street to Santa Rosa Street to include the widening of a sidewalk under the IH-35 underpass, sidewalk extensions at Old Concho Street, the addition of paver sidewalks, a High-Intensity Activated Crosswalk (HAWK) signal at Leona Street, upgrades to existing traffic signals to meet American with Disabilities Act (ADA) requirements and pedestrian lighting and landscape improvements east of Pecos La Trinidad. Project construction is anticipated to begin May 2019 and estimated to be completed February 2020.

Procurement of Services
This project was advertised for construction bids in the San Antonio Hart Beat, on the City's website, on the Texas Electronic State Business Daily, through CIVCAST electronic bidding site and on TVSA. Bids were opened on February 26, 2019 and three (3) bids were received. Of these, Jerdon Enterprise, L.P. submitted the lowest responsive bid.

This contract will be awarded in compliance with the new Small Business Economic Development Advocacy (SBEDA) Program, which requires contracts to be reviewed by a Goal Setting Committee to establish a requirement and/or incentive unique to the particular con...