File #: 19-5274   
Type: Capital Improvements
In control: City Council A Session
On agenda: 8/22/2019
Posting Language: Ordinance approving an Advanced Funding Agreement with the Texas Department of Transportation (TxDOT); accepting reimbursement in an amount not to exceed $8,712,000.00 from TxDOT for construction-related expenses; and approving payment in an amount not to exceed $114,394.00 to TxDOT for administrative oversight of federal funds for Presa Road Complete Streets, a S. Presa Street (S.E. Military Drive to Southcross Boulevard) 2017-2022 Bond and federally funded project. [Roderick Sanchez, Assistant City Manager; Razi Hosseini, Interim Director, Transportation & Capital Improvements]
Attachments: 1. S. Presa Map, 2. Approved for partial execution _0915-12-604 AFA-LPAFA_COSA, 3. Draft Ordinance, 4. Staff Presentation, 5. Ordinance 2019-08-22-0651
DEPARTMENT: Transportation & Capital Improvements


DEPARTMENT HEAD: Razi Hosseini, P.E., R.P.L.S.


COUNCIL DISTRICTS IMPACTED: 3 & 5


SUBJECT: Advanced Funding Agreement: Presa Road Complete Streets


SUMMARY:

An ordinance authorizing the execution of an Advanced Funding Agreement between the City of San Antonio and the Texas Department of Transportation (TxDOT), accepting reimbursement in the estimated amount not to exceed $8,712,000.00 from TxDOT for construction-related expenses and authorizing payment in the amount not to exceed $114,394.00 to TxDOT for administrative oversight of federal funds for Presa Road Complete Streets, a S. Presa Street (S.E. Military Drive to Southcross Boulevard) 2017-2022 Bond and federally funded project located in Council Districts 3 and 5.


BACKGROUND INFORMATION:

Project Background
The Presa Road Complete Streets project to be delivered as part of the 2017-2022 Bond Program as S. Presa Street (S.E. Military Drive to Southcross Boulevard) Project was selected for funding through the Alamo Area Metropolitan Planning Organization (AAMPO) Transportation Improvement Program (TIP). Local Agency Managed projects are managed by the City but receive federal funds administered through TxDOT. The funds paid to TxDOT by the City are for costs associated with oversight for administration of the federal funds.

The Presa Road Complete Streets project, also referred to as S. Presa Street (S.E. Military Drive to Southcross Boulevard) Project, will provide for pedestrian connectivity by constructing sidewalks, curbs and driveway approaches from W. Boyer Street to S.E. Military Drive including roadway improvements along the Presa corridor, ponding relief around Story Lane, Wahrmund Court and Koehler Court intersections and traffic signal upgrades. The City will design and construct the improvements leveraging funding from TxDOT. Project construction is anticipated to begin in May 2020 and estimated to be completed by October 2021.

Previo...