Posting Language: Ordinance amending the Contribution Agreement with Civita S Corp 2019 in an amount not to exceed $300,000.00 for reimbursement to Civita S Corp 2019 of construction phase engineering services related to the West Military Drive & Ingram Road Connectors project, a 2017 Bond funded project. [Roderick Sanchez, Assistant City Manager; Razi Hosseini, Interim Director, Transportation & Capital Improvements]
Attachments: 1. Ingram Rd & W Military Hywy Extension Projects RFCA Map, 2. Military Ingram Amendment, 3. Draft Ordinance, 4. Staff Presentation, 5. Ordinance 2020-03-05-0157
DEPARTMENT: Transportation & Capital Improvements


DEPARTMENT HEAD: Razi Hosseini, P.E., R.P.L.S


COUNCIL DISTRICTS IMPACTED: Council District 6


SUBJECT:

Contribution Agreement Amendment: West Military Drive & Ingram Road Connectors


SUMMARY:

An ordinance authorizing the execution of an amendment to a Contribution Agreement between the City of San Antonio and Civita S Corp 2019 in the amount not to exceed $300,000.00 for the payment from the City of San Antonio to Civita S Corp 2019 for reimbursement of construction phase engineering services related to the West Military Drive & Ingram Road Connectors project, a 2017 Bond funded project, located in Council District 6.


BACKGROUND INFORMATION:

Project Background
On May 6, 2017, San Antonio voters approved the 2017-2022 Bond Program, consisting of six propositions totaling $850 Million to be used on various capital improvement projects to address community infrastructure needs and improve the overall quality of life in San Antonio. As part of Proposition 1 Streets, Bridges & Sidewalk Improvements, funds in the amount of $10,000,000.00 associated with the West Military Drive & Ingram Road Connectors Project and $1,000,000.00 for the Ingram Road (Potranco Road to Dead End) were approved for improvements associated with West Military Drive & Ingram Road Connectors Project.

The project supports the thoroughfare plan extension of W. Military Drive connecting from Potranco Road, including the extension of Ingram Road to Potranco. The project will include street, curbs, sidewalks, bike facilities, an intersection, a traffic signal and drainage improvements. Project Construction began in July 2019 and is estimated to be complete by July 2020.

Previous Council Action
A previously executed Contribution Agreement with Civita S Corp 2019 for the West Military Drive & Ingram Road Connectors project pursuant to which Civita S Corp 2019 contributed right-of-way and engineering costs and the City provided cons...