File #: 20-6605   
Type: Capital Improvements
In control: City Council A Session
On agenda: 12/10/2020
Posting Language: Ordinance approving a City requested change order in the increased amount of $228,960.00 and authorizing payment to ASD Consultants, Inc. to install trees and irrigation related to the San Pedro Springs Park project, a 2017 Bond funded project, located in Council District 1; and authorizing the appropriation and amending of the FY 2021 - FY 2026 Capital Improvement Program with funds in the amount of $228,960.00 from the Tree Canopy Preservation and Mitigation Fund to the San Pedro Springs Park project. [Roderick Sanchez, Assistant City Manager; Razi Hosseini, Director, Public Works]
Attachments: 1. Map - San Pedro.pdf, 2. Proposal_Trees Quote.pdf, 3. Ordinance 2020-12-10-0888
DEPARTMENT: Public Works


DEPARTMENT HEAD: Razi Hosseini, P.E., R.P.L.S.


COUNCIL DISTRICTS IMPACTED: Council District 1


SUBJECT:

Change Order: San Pedro Springs Park (2017 Bond Project)


SUMMARY:

An ordinance approving a City requested change order in the increased amount of $228,960.00 and authorizing payment to ASD Consultants, Inc. to install trees and irrigation related to the San Pedro Springs Park project, a 2017 Bond funded project, located in Council District 1; and authorizing the appropriation and amending of the FY 2021 - FY 2026 Capital Improvement Program with funds in the amount of $228,960.00 from the Tree Canopy Preservation and Mitigation Fund to the San Pedro Springs Park project.

BACKGROUND INFORMATION:

Project Background
On May 6, 2017, voters approved the 2017 Bond Program, which included funds in the amount of $1,800,000.00 for general park improvements associated with the San Pedro Springs Park located in Council District 1. The general park improvements include the removal of the existing softball fields, construction of a new walking trail equipped with pedestrian lighting and benches, parking modifications, lighting and electrical upgrades, new sidewalks, historic acequia repairs, accessibility modifications, landscaping and irrigation. Also included, as part of this project, is the installation of a sign monument on the corner of San Pedro Avenue and Myrtle Avenue. Construction began in October 2020 and is estimated to be completed by May 2021.

Previous Council Action
On August 8, 2020, City Council approved a construction contract in the amount of $1,119,347.00 with ASD Consultants, Inc. through Ordinance 2020-08-20-0545 for the San Pedro Springs Park project. Funds in the amount of $228,960.00 for tree installation and irrigation were not included in this original contract. This change order will add these funds to the contract with ASD Consultants, Inc. to install trees and irrigation associated with San Pedro Spr...

Click here for full text