File #: 21-3672   
Type: Capital Improvements
In control: City Council A Session
On agenda: 6/17/2021
Posting Language: Ordinance approving a Professional Services Agreement in an amount not to exceed $1,260,000.00 payable to Marmon Mok, LP for design and construction administration services related to the Architectural Services for Alamodome Improvements Project. Funds are available from Certificates of Obligation and are included in the FY 2021 - FY 2026 Capital Improvement Program. [Roderick Sanchez, Assistant City Manager; Razi Hosseini, Director, Public Works]
Attachments: 1. Alamodome Improvements_Map.pdf, 2. Scoring Matrix_Alamodome Improvements, 3. Contracts Disclosure - Marmon Mok.pdf, 4. Draft Agreement_Alamodome Improvements, 5. Draft Ordinance, 6. Ordinance 2021-06-17-0463
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
DEPARTMENT: Public Works


DEPARTMENT HEAD: Razi Hosseini, P.E., R.P.L.S.


COUNCIL DISTRICTS IMPACTED: Council District 2


SUBJECT:

Contract Award: Architectural Services for Alamodome Improvements Project
SUMMARY:

An ordinance approving the negotiation and execution of a Professional Services Agreement in an amount not to exceed $1,260,000.00 payable to Marmon Mok, LP for design and construction administration services related to the Architectural Services for Alamodome Improvements Project. Funds are available from Certificates of Obligation and are included in the FY 2021 - FY 2026 Capital Improvement Program.


BACKGROUND INFORMATION:

Project Background
The Alamodome opened on May 15, 1993, at a cost of approximately $186 million and is owned and operated by the City. This multi-purpose facility is the preferred venue for many trade shows, sporting events and concerts such as Monster Jam, Disney on Ice and the Valero Alamo Bowl. The Alamodome was also home to the NBA World Champion San Antonio Spurs from 1993 to 2002.

As part of the City's commitment to hosting the 2018 NCAA Men's Final Four, the Convention & Sports Facilities Department completed an expansion project at the Alamodome which added a 24,000 square foot, state-of-the-art field level multipurpose room designed for postgame interviews and press conferences. This project also provided an additional 26,000 square foot east and west concourse expansion to include exterior Beer Gardens complementing the renovated concession areas.

As the City continues its success in hosting NCAA events, the City has committed to additional interior improvements at the Alamodome in preparation for the NCAA Men's Final Four in 2025. The improvements included as part of this project will consist of new club and mezzanine-level suites as well as renovations to the concession and circulation areas with similar enhancements as previously completed in the east and west sides of the Plaza Level. This agree...