city of San Antonio


Some of our meetings have moved. View additional meetings.

File #: 20-1496   
Type: Capital Improvements
In control: City Council A Session
On agenda: 3/5/2020
Posting Language: Ordinance approving a construction contract including two additive alternates in the amount of $200,266.00 to Jerdon Enterprise, LP for the Cuellar Park project, a 2017 Bond funded project. [Roderick Sanchez, Assistant City Manager; Razi Hosseini, Interim Director, Transportation & Capital Improvements]
Attachments: 1. Map_Cuellar Park, 2. Staff Presentation, 3. Ordinance 2020-03-05-0161
DEPARTMENT: Transportation & Capital Improvements


DEPARTMENT HEAD: Razi Hosseini, P.E., R.P.L.S


COUNCIL DISTRICTS IMPACTED: Council District 6


SUBJECT:

Contract Award: Cuellar Park (2017 Bond Project)


SUMMARY:

An ordinance accepting the lowest responsive bid and awarding a construction contract including two additive alternates in the amount of $200,266.00 to Jerdon Enterprise, LP for the Cuellar Park project, a 2017 Bond funded project, located in Council District 6.


BACKGROUND INFORMATION:

Project Background
The approved 2017 Bond Program included $368,000.00 for Cuellar Park. Improvements to the park will include a large, lighted pavilion with picnic tables and trash receptacles near the northern playground with sidewalk, as well as lighting upgrades to the existing light poles in the area of the playground for safety after hours. The two additive alternates identified as part of this project will include four pedestrian trail lights and field lighting for one of the existing little league fields. Construction is anticipated to begin in April 2020 and estimated to be completed by September 2020.

Procurement of Services
This project was advertised on November 18, 2019 for construction bids in the San Antonio Hart Beat, on the City's website, on the Texas Electronic State Business Daily, on TVSA, through the electronic bidding site CivCast and through the TCI Small Business Office. Bids were opened on January 7, 2020 and eight (8) bids were received. Of these, Jerdon Enterprise, LP submitted the lowest responsive bid. A matrix of the bid outcome is included herein.

This contract will be awarded in compliance with the new Small Business Economic Development Advocacy (SBEDA) Program, which requires contracts to be reviewed by a Goal Setting Committee to establish a requirement and/or incentive unique to the particular contract in an effort to maximize the amount of small, minority and women-owned business participation on the contract. Th...